A practical approach to resource - constrained project scheduling

被引:0
|
作者
John-Paris Pantouvakis
Odysseus G. Manoliadis
机构
[1] National Technical University of Athens,Department of Construction Engineering & Management, Faculty of Civil Engineering
[2] Technological Educational Institute of Western Macedonia,Department of Geotechnology and Environmental Engineering
关键词
time scheduling; leveling; resources; constraints;
D O I
10.1007/BF02941258
中图分类号
学科分类号
摘要
In this paper a solution approach is discussed for managing projects with resource constraints. For this purpose a heuristic method is developed based on traditional CPM scheduling calculations and leveling algorithms. The method can be applied using normal scheduling software such as P3 and MS project, and as such, it is of value to practitioners. An illustrative example is also presented herein to exemplify the concepts. The problem solved has importance and direct application to the management of a wide variety of project-structured efforts with prevailing resource constraints.
引用
收藏
页码:299 / 309
页数:10
相关论文
共 50 条
  • [31] A New Resource Constrained Project Scheduling Problem
    Liu, Xiaoxiang
    Jiang, Weigang
    Xie, Jianwen
    Jia, Yitian
    [J]. 2009 ASIA-PACIFIC CONFERENCE ON INFORMATION PROCESSING (APCIP 2009), VOL 1, PROCEEDINGS, 2009, : 476 - +
  • [32] Weighted Multi-Skill Resource Constrained Project Scheduling: A Greedy and Parallel Scheduling Approach
    Akbar, Saeed
    Zubair, Muhammad
    Khan, Rizwan
    Ul Akbar, Ubaid
    Ullah, Rahmat
    Zheng, Zhonglong
    [J]. IEEE ACCESS, 2024, 12 : 29824 - 29836
  • [33] A Population-Based Approach to the Resource-Constrained Project Scheduling Problem
    Vicente Valls
    Francisco Ballestín
    Sacramento Quintanilla
    [J]. Annals of Operations Research, 2004, 131 : 305 - 324
  • [34] A population-based approach to the resource-constrained project scheduling problem
    Valls, V
    Ballestín, F
    Quintanilla, S
    [J]. ANNALS OF OPERATIONS RESEARCH, 2004, 131 (1-4) : 305 - 324
  • [35] AN ITERATIVE SCHEDULING TECHNIQUE FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING
    LI, KY
    WILLIS, RJ
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1992, 56 (03) : 370 - 379
  • [36] Robust global and local search approach to resource-constrained project scheduling
    Kim, Jin-Lee
    Ellis, Ralph D., Jr.
    [J]. CANADIAN JOURNAL OF CIVIL ENGINEERING, 2009, 36 (03) : 375 - 388
  • [37] Agent-based approach to solving the resource constrained project scheduling problem
    Jedrzejowicz, Piotr
    Ratajczak-Ropel, Ewa
    [J]. ADAPTIVE AND NATURAL COMPUTING ALGORITHMS, PT 1, 2007, 4431 : 480 - +
  • [38] The multiple resource constrained project scheduling problem: A breadth-first approach
    Nazareth, T
    Verma, S
    Bhattacharya, S
    Bagchi, A
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (02) : 347 - 366
  • [39] A matheuristic approach to the multi-mode resource constrained project scheduling problem
    Fernandes, Gustavo Alves
    de Souza, Sergio Ricardo
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2021, 162
  • [40] Resource-constrained project scheduling - Minimization of project duration
    不详
    [J]. PROJECT SCHEDULING WITH TIME WINDOWS AND SCARCE RESOURCES, 2002, 508 : 21 - 174