This paper presents the experience on how Entergy Transmission Engineering Group started the IEC 61850 effort together with collaborators such as vendors, research institutes, utility companies, and standard committee. The project was initially started with the intension to learn about the technology and had gradually evolved into an open platform testbed for multivendor interoperability of their Intelligent Electronics Devices (IED), which eventually had gained support and interest to start a pilot project to deploy a parallel IEC 61850 process bus system into one of the substations in New Orleans - Joliet Sub. This paper will share the goals and the design of the pilot substation, Joliet and future design concepts of Entergy's next digital substation.
引用
收藏
页数:8
相关论文
共 50 条
  • [21] IEC 61850 BASED SUBSTATION AUTOMATION SYSTEM ARCHITECTURE DESIGN
    Tan, Jian-cheng
    Luan, Wenpeng
    2011 IEEE POWER AND ENERGY SOCIETY GENERAL MEETING, 2011,
  • [22] Design and Simulation of Fast Substation Protection in IEC 61850 Environments
    Valdes, Alfonso
    Hang, Cui
    Panumpabi, Prosper
    Vaidya, Nitin
    Drew, Chris
    Ischenko, Dimitry
    2015 WORKSHOP ON MODELING AND SIMULATION OF CYBER-PHYSICAL ENERGY SYSTEMS (MSCPES), 2015,
  • [23] Network Interactions and Performance of a Multifunction IEC 61850 Process Bus
    Ingram, David M. E.
    Schaub, Pascal
    Taylor, Richard R.
    Campbell, Duncan A.
    IEEE TRANSACTIONS ON INDUSTRIAL ELECTRONICS, 2013, 60 (12) : 5933 - 5942
  • [24] A distributed recording system based on IEC 61850 process bus
    Apostolov, A.
    Auperrin, F.
    Passet, R.
    Guenego, M.
    Gilles, F.
    2006 POWER SYSTEMS CONFERENCE ADVANCED METERING, PROTECTION, CONTROL, COMMUNICATION, AND DISTRIBUTED RESOURCES, 2006, : 57 - +
  • [25] A Quantitative Evaluation of IEC61850 Process Bus Architectures
    Tournier, Jean-Charles
    Werner, Thomas
    IEEE POWER AND ENERGY SOCIETY GENERAL MEETING 2010, 2010,
  • [26] IEC 61850 process bus based distributed waveform recording
    Apostolov, A.
    Auperrin, F.
    Passet, R.
    Guenego, M.
    Gilles, F.
    2006 POWER ENGINEERING SOCIETY GENERAL MEETING, VOLS 1-9, 2006, : 2177 - +
  • [27] Verification of the performance of IEC 61850 Sampled Values in Process Bus
    Daboul, Mayada
    Orsagova, Jaroslava
    PROCEEDINGS OF THE 7TH INTERNATIONAL SCIENTIFIC SYMPOSIUM ON ELECTRICAL POWER ENGINEERING (ELEKTROENERGETIKA 2013), 2013, : 466 - 469
  • [28] Practical Experience with IEEE 1588 High Precision Time Synchronization in Electrical Substation based on IEC 61850 Process Bus
    Moore, R.
    Midence, R.
    Goraj, M.
    IEEE POWER AND ENERGY SOCIETY GENERAL MEETING 2010, 2010,
  • [29] Design of substation configuration tool based on IEC61850 standards
    Wang, Feng-Xiang
    Fang, Chun-En
    Li, Wei
    Dianli Xitong Baohu yu Kongzhi/Power System Protection and Control, 2010, 38 (10): : 106 - 109
  • [30] IEC 61850 Application in Intelligent Substation Automation
    Gao, Guangling
    Pan, Xianghua
    Cheng, Xueyang
    2015 4TH INTERNATIONAL CONFERENCE ON ENERGY AND ENVIRONMENTAL PROTECTION (ICEEP 2015), 2015, : 2472 - 2477