A high performing metaheuristic for job shop scheduling with sequence-dependent setup times

被引:34
|
作者
Naderi, B. [1 ]
Ghomi, S. M. T. Fatemi [1 ]
Aminnayeri, M. [1 ]
机构
[1] Amir Kabir Univ Technol, Dept Ind Engn, Tehran, Iran
关键词
Scheduling; Job shop; Sequence-dependent setup times; Simulated annealing; Taguchi method; SIMULATED ANNEALING ALGORITHM; GENETIC ALGORITHMS; IMMUNE ALGORITHM; BOUND METHOD; SEARCH; COSTS;
D O I
10.1016/j.asoc.2009.08.039
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
This paper investigates scheduling job shop problems with sequence-dependent setup times under minimization of makespan. We develop an effective metaheuristic, simulated annealing with novel operators, to potentially solve the problem. Simulated annealing is a well-recognized algorithm and historically classified as a local-search-based metaheuristic. The performance of simulated annealing critically depends on its operators and parameters, in particular, its neighborhood search structure. In this paper, we propose an effective neighborhood search structure based on insertion neighborhoods as well as analyzing the behavior of simulated annealing with different types of operators and parameters by the means of Taguchi method. An experiment based on Taillard benchmark is conducted to evaluate the proposed algorithm against some effective algorithms existing in the literature. The results show that the proposed algorithm outperforms the other algorithms. (C) 2009 Elsevier B. V. All rights reserved.
引用
收藏
页码:703 / 710
页数:8
相关论文
共 50 条
  • [41] Modeling and optimization of the hybrid flow shop scheduling problem with sequence-dependent setup times
    Xue, Huiting
    Meng, Leilei
    Duan, Peng
    Zhang, Biao
    Zou, Wenqiang
    Sang, Hongyan
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING COMPUTATIONS, 2024, 15 (02) : 473 - 490
  • [42] Scheduling hybrid flow shop with sequence-dependent setup times and machines with random breakdowns
    M. Gholami
    M. Zandieh
    A. Alem-Tabriz
    The International Journal of Advanced Manufacturing Technology, 2009, 42 : 189 - 201
  • [43] Scheduling hybrid flow shop with sequence-dependent setup times and machines with random breakdowns
    Gholami, M.
    Zandieh, M.
    Alem-Tabriz, A.
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 42 (1-2): : 189 - 201
  • [44] Reinsertion principles for multi-resource shop scheduling with sequence-dependent setup times
    Artigues, C
    Roubellat, F
    MANAGEMENT AND CONTROL OF PRODUCTION AND LOGISTICS, VOL 1 AND 2, 1998, : 307 - 313
  • [45] Solving the flexible job shop scheduling problem with sequence-dependent setup times (vol 265, pg 503, 2018)
    Shen, Liji
    Dauzere-Peres, Stephane
    Neufeld, Janis S.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2022, 296 (02) : 748 - 748
  • [46] A Fuzzy-Genetic Algorithm for a Re-entrant Job Shop Scheduling Problem with Sequence-Dependent Setup Times
    Dehghanian, Negin
    Homayouni, S. Mahdi
    2013 13TH IRANIAN CONFERENCE ON FUZZY SYSTEMS (IFSC), 2013,
  • [47] Job shop scheduling with separable sequence-dependent setups
    In-Chan Choi
    Osman Korkmaz
    Annals of Operations Research, 1997, 70 : 155 - 170
  • [48] A flexible job shop cell scheduling with sequence-dependent family setup times and intercellular transportation times using conic scalarization method
    Deliktas, Derya
    Torkul, Orhan
    Ustun, Ozden
    INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2019, 26 (06) : 2410 - 2431
  • [49] An approach to job shop scheduling with sequence-dependent setups
    Sun, XQ
    Noble, JS
    JOURNAL OF MANUFACTURING SYSTEMS, 1999, 18 (06) : 416 - 430
  • [50] Job shop scheduling with separable sequence-dependent setups
    Choi, IC
    Korkmaz, O
    ANNALS OF OPERATIONS RESEARCH, 1997, 70 (0) : 155 - 170