Planning India's long-term energy shipment infrastructures for electricity and coal

被引:4
|
作者
Bowen, Brian H. [1 ]
Canchi, Devendra [1 ]
Lalit, Vishal Agarwal [1 ]
Preckel, Paul V. [1 ]
Sparrow, F. T. [1 ]
Irwin, Marty W. [1 ]
机构
[1] Purdue Univ, Energy Ctr Discovery Pk, W Lafayette, IN 47907 USA
关键词
India power grid; Electricity system planning; Coal policy;
D O I
10.1016/j.enpol.2009.09.033
中图分类号
F [经济];
学科分类号
02 ;
摘要
The Purdue Long-Term Electricity Trading and Capacity Expansion Planning Model simultaneously optimizes both transmission and generation capacity expansions. Most commercial electricity system planning software is limited to only transmission planning. An application of the model to India's national power grid, for 2008-2028, indicates substantial transmission expansion is the cost-effective means of meeting the needs of the nation's growing economy. An electricity demand growth rate of 4% over the 20-year planning horizon requires more than a 50% increase in the Government's forecasted transmission capacity expansion, and 8% demand growth requires more than a six-fold increase in the planned transmission capacity expansion. The model minimizes the long-term expansion costs (operational and capital) for the nation's five existing regional power grids and suggests the need for large increases in load-carrying capability between them. Changes in coal policy affect both the location of new thermal power plants and the optimal pattern inter-regional transmission expansions. (C) 2009 Elsevier Ltd. All rights reserved.
引用
收藏
页码:432 / 444
页数:13
相关论文
共 50 条
  • [21] Development of Rwanda's Future Energy Scenarios for Long-Term Investment and Planning
    Mudaheranwa, Emmanuel
    Masengo, G.
    Odoakah, Ye-Obong
    Cipcigan, Liana
    Ugalde-Loo, Carlos E.
    2021 3RD ASIA ENERGY AND ELECTRICAL ENGINEERING SYMPOSIUM (AEEES 2021), 2021, : 1124 - 1129
  • [22] Overview of long-tern electricity demand forecasting mechanism for national long-term electricity resource planning
    Kim, Wan-Soo
    Jeon, Byung-Kyu
    Transactions of the Korean Institute of Electrical Engineers, 2010, 59 (09): : 1581 - 1586
  • [23] Long-Term Storage and Shipment of Spent Nuclear Fuel
    Yu. V. Kozlov
    V. D. Safutin
    N. S. Tikhonov
    A. I. Tokarenko
    V. V. Spichev
    Atomic Energy, 2000, 89 : 792 - 803
  • [24] Long-term storage and shipment of spent nuclear fuel
    Kozlov, YV
    Safutin, VD
    Tikhonov, NS
    Tokarenko, AI
    Spichev, VV
    ATOMIC ENERGY, 2000, 89 (04) : 792 - 803
  • [25] LONG-TERM PLANNING FOR SOLID-WASTE MANAGEMENT IN INDIA
    SHEKDAR, AV
    KRISHNASWAMY, KN
    TIKEKAR, VG
    BHIDE, AD
    WASTE MANAGEMENT & RESEARCH, 1991, 9 (06) : 511 - 523
  • [26] Novel methodology for efficiency-based long-term investment planning in water infrastructures
    Vieira, Joao
    Cabral, Marta
    Almeida, Nuno
    Silva, Jaime Gabriel
    Covas, Didia
    STRUCTURE AND INFRASTRUCTURE ENGINEERING, 2020, 16 (12) : 1654 - 1668
  • [27] NEW REQUIREMENTS ON LONG-TERM PLANNING OF ENERGY INDUSTRIES
    HEDRICH, P
    UFER, D
    ENERGIETECHNIK, 1978, 28 (05): : 166 - 168
  • [28] Long-term energy planning and the role of forest biomass
    Berni, Mauro
    O Papel, 2020, 81 (09): : 78 - 79
  • [29] Long-term energy demand forecasting and planning in Taiwan
    Bor, YJ
    Liu, SM
    Jan, HK
    Chou, FY
    ENERGY AND ECONOMIC GROWTH: IS SUSTAINABLE GROWTH POSSIBLE?, VOLS 1-3, 1997, : 305 - 315
  • [30] Macroeconomic Models for Long-term Energy and Emissions in India
    Ashish Rana
    P. R. Shukla
    OPSEARCH, 2001, 38 (1) : 87 - 108