Time-cost trade-off analysis of a priority based assignment problem

被引:0
|
作者
Kaur, Prabhjot [1 ]
Dahiya, Kalpana [1 ]
Verma, Vanita [2 ]
机构
[1] Panjab Univ, UIET, Chandigarh 160014, India
[2] Panjab Univ, Dept Math, Chandigarh 160014, India
关键词
Optimization; Non-linear programming; Assignment problem; Bi-objective; Efficient solutions; ALGORITHM; TREES;
D O I
10.1007/s12597-020-00483-4
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
In this paper, a bi-objective priority based assignment problem (BPBAP) related to an industrial project, is considered in which, depending upon the work breakdown structure, the n tasks involved in the project are divided into two categories. One of the categories consists of m primary tasks and the other one consists of ( n - m) secondary tasks (for m < n). The project is such that the secondary tasks can be executed only after the primary tasks are finished, however, the tasks within each category may be executed simultaneously. This problem is a special case of categorized assignment scheduling problem, discussed extensively in literature. The BPBAP is studied with the objective of minimizing simultaneously, the two criteria namely, total execution time and total assignment cost of the project which are equal to the sum of execution times and assignment costs respectively, of primary and secondary tasks. Generally, it is not possible to optimize both the objectives simultaneously, therefore, there is a need to do time-cost trade-off analysis of the problem. Since, the present problem is based on two-stage execution of the project (one stage for each category of tasks), therefore, a criteria based iterative algorithm considering all the possible combinations of the parameters of both the categories, is developed that finds all the non-dominated points of BPBAP in a polynomial time. Numerical illustrations are provided in the support of theory.
引用
收藏
页码:448 / 482
页数:35
相关论文
共 50 条
  • [31] Resource Constrained Time-cost Trade-off Problem and its Genetic Algorithm Solution
    Feng, Yixiong
    Lin, Xiaohua
    Tan, Jianrong
    [J]. APPLIED MATHEMATICS & INFORMATION SCIENCES, 2013, 7 (02): : 639 - 643
  • [32] A new approach to solve time-cost trade-off problem with fuzzy decision variables
    Ghazanfari, M.
    Yousefli, A.
    Ameli, M. S. Jabal
    Bozorgi-Amiri, A.
    [J]. INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 42 (3-4): : 408 - 414
  • [33] A Dependent-Chance Programming Model for Fuzzy Time-Cost Trade-off Problem
    Ke, Hua
    Ma, Weimin
    [J]. 2009 IEEE INTERNATIONAL CONFERENCE ON FUZZY SYSTEMS, VOLS 1-3, 2009, : 2183 - 2186
  • [34] Optimization of construction time-cost trade-off analysis using genetic algorithms
    Hegazy, T
    [J]. CANADIAN JOURNAL OF CIVIL ENGINEERING, 1999, 26 (06) : 685 - 697
  • [35] Time-cost trade-off of construction project based on ant colony algorithm
    Xiong, Ying
    Kuang, Ya-Ping
    [J]. Xitong Gongcheng Lilun yu Shijian/System Engineering Theory and Practice, 2007, 27 (03): : 105 - 111
  • [36] Multivariate Analysis on Time-Cost Trade-Off for Production and Installation in Industrialized Construction
    Xie, Haiyan
    Sumam, Rugma Jayachandrakumar
    Carey, Nicholas
    [J]. CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 281 - 290
  • [37] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES - DISCUSSION
    HANSCOM, GB
    WAUGH, L
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (02): : 374 - 375
  • [39] TIME-COST TRADE-OFF AMONG RELATED ACTIVITIES - CLOSURE
    REDA, R
    CARR, RI
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (02): : 375 - 376
  • [40] Pareto Front Particle Swarm Optimizer for Discrete Time-Cost Trade-Off Problem
    Aminbakhsh, Saman
    Sonmez, Rifat
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (01)