Memetic algorithm for multi-mode resource-constrained project scheduling problems

被引:7
|
作者
Liu, Shixin [1 ]
Chen, Di [1 ]
Wang, Yifan [1 ]
机构
[1] Northeastern Univ, Coll Informat Sci & Engn, Shenyang 110819, Peoples R China
基金
中国国家自然科学基金;
关键词
project scheduling; resource-constrained; multi-mode; memetic algorithm (MA); local search procedure; GENETIC ALGORITHM; MULTIPLE-MODES; OPTIMIZATION; SEARCH;
D O I
10.1109/JSEE.2014.00071
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
A memetic algorithm (MA) for a multi-mode resource-constrained project scheduling problem (MRCPSP) is proposed. We use a new fitness function and two very effective local search procedures in the proposed MA. The fitness function makes use of a mechanism called "strategic oscillation" to make the search process have a higher probability to visit solutions around a "feasible boundary". One of the local search procedures aims at improving the lower bound of project makespan to be less than a known upper bound, and another aims at improving a solution of an MRCPSP instance accepting infeasible solutions based on the new fitness function in the search process. A detailed computational experiment is set up using instances from the problem instance library PSPLIB. Computational results show that the proposed MA is very competitive with the state-of-the-art algorithms. The MA obtains improved solutions for one instance of set J30.
引用
收藏
页码:609 / 617
页数:9
相关论文
共 50 条
  • [1] Memetic algorithm for multi-mode resource-constrained project scheduling problems
    Shixin Liu
    Di Chen
    Yifan Wang
    [J]. Journal of Systems Engineering and Electronics, 2014, 25 (04) : 609 - 617
  • [2] Hybrid genetic algorithm for multi-mode resource-constrained project scheduling problems
    School of Economics and Management, Southeast University, Nanjing 210096, China
    [J]. Dongnan Daxue Xuebao, 2008, 4 (736-740):
  • [3] Scatter Search for Multi-mode Resource-constrained Project Scheduling Problems
    Pourghaderi, A. R.
    Torabi, S. A.
    Talebi, J.
    [J]. IEEM: 2008 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-3, 2008, : 163 - 167
  • [4] A Dual-Population Memetic Algorithm for Minimizing Total Cost of Multi-Mode Resource-Constrained Project Scheduling
    Chen, Zhi-Jie
    Chyu, Chiuh-Cheng
    [J]. INDUSTRIAL ENGINEERING AND MANAGEMENT SYSTEMS, 2010, 9 (02): : 70 - 79
  • [5] Bees Algorithm for multi-mode, resource-constrained project scheduling in molding industry
    Oztemel, Ercan
    Selam, Ayse Aycim
    [J]. COMPUTERS & INDUSTRIAL ENGINEERING, 2017, 112 : 187 - 196
  • [6] Differential evolution for solving multi-mode resource-constrained project scheduling problems
    Damak, N.
    Jarboui, B.
    Siarry, P.
    Loukil, T.
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2009, 36 (09) : 2653 - 2659
  • [7] Simulated Annealing for Multi-Mode Resource-Constrained Project Scheduling
    Joanna Józefowska
    Marek Mika
    Rafał Różycki
    Grzegorz Waligóra
    Jan Węglarz
    [J]. Annals of Operations Research, 2001, 102 : 137 - 155
  • [8] Resource-constrained project scheduling: a heuristic for the multi-mode case
    Heilmann, R
    [J]. OR SPEKTRUM, 2001, 23 (03) : 335 - 357
  • [9] Simulated annealing for multi-mode resource-constrained project scheduling
    Józefowska, J
    Mika, M
    Rózycki, R
    Waligóra, G
    Weglarz, J
    [J]. ANNALS OF OPERATIONS RESEARCH, 2001, 102 (1-4) : 137 - 155
  • [10] Modelling and Solving Multi-mode Resource-Constrained Project Scheduling
    Szeredi, Ria
    Schutt, Andreas
    [J]. PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING, CP 2016, 2016, 9892 : 483 - 492