Single machine scheduling problem with stochastic sequence-dependent setup times

被引:20
|
作者
Ertem, Mehmet [1 ]
Ozcelik, Feristah [1 ]
Sarac, Tugba [1 ]
机构
[1] Eskisehir Osmangazi Univ, Dept Ind Engn, Eskisehir, Turkey
关键词
single machine scheduling problem; stochastic sequence-dependent setup times; Genetic Algorithm; stochastic programming; value of the stochastic solution; TARDY JOBS; GENETIC ALGORITHM; PROCESSING TIMES; TOTAL TARDINESS; EXPECTED NUMBER; BOUNDED SETUP; SUPPLY CHAIN; FLOWSHOP; MINIMIZE; OPTIMIZATION;
D O I
10.1080/00207543.2019.1581383
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In this study, we consider stochastic single machine scheduling problem. We assume that setup times are both sequence dependent and uncertain while processing times and due dates are deterministic. In the literature, most of the studies consider the uncertainty on processing times or due dates. However, in the real-world applications (i.e. plastic moulding industry, appliance assembly, etc.), it is common to see varying setup times due to labour or setup tools availability. In order to cover this fact in machine scheduling, we set our objective as to minimise the total expected tardiness under uncertain sequence-dependent setup times. For the solution of this NP-hard problem, several heuristics and some dynamic programming algorithms have been developed. However, none of these approaches provide an exact solution for the problem. In this study, a two-stage stochastic-programming method is utilised for the optimal solution of the problem. In addition, a Genetic Algorithm approach is proposed to solve the large-size problems approximately. Finally, the results of the stochastic approach are compared with the deterministic one to demonstrate the value of the stochastic solution.
引用
收藏
页码:3273 / 3289
页数:17
相关论文
共 50 条
  • [41] Heuristics for the Hybrid Flow Shop Scheduling Problem with Sequence-Dependent Setup times
    Yong, Liao
    Zhantao, Li
    Xiang, Li
    Chenfeng, Peng
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2022, 2022
  • [42] Customer order scheduling problem to minimize makespan with sequence-dependent setup times
    Prata, Bruno de Athayde
    Rodrigues, Carlos Diego
    Framinan, Jose Manuel
    COMPUTERS & INDUSTRIAL ENGINEERING, 2021, 151
  • [43] Two approaches to handle the dynamism in a scheduling problem with sequence-dependent setup times
    Angel-Bello, Francisco
    Vallikavungal, Jobish
    Alvarez, Ada
    EXPERT SYSTEMS WITH APPLICATIONS, 2021, 167
  • [44] Tractable Risk Measures for the Selective Scheduling Problem with Sequence-Dependent Setup Times
    Bruni, M. E.
    Khodaparasti, S.
    OPERATIONS RESEARCH AND ENTERPRISE SYSTEMS, ICORES 2019, 2020, 1162 : 70 - 84
  • [45] Solving the flexible job shop scheduling problem with sequence-dependent setup times
    Shen, Liji
    Dauzere-Peres, Stephane
    Neufeld, Janis S.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 265 (02) : 503 - 516
  • [46] A heuristic approach for a scheduling problem with periodic maintenance and sequence-dependent setup times
    Angel-Bello, Francisco
    Alvarez, Ada
    Pacheco, Joaquin
    Martinez, Iris
    COMPUTERS & MATHEMATICS WITH APPLICATIONS, 2011, 61 (04) : 797 - 808
  • [47] A Matheuristic Approach to the Open Shop Scheduling Problem with Sequence-Dependent Setup Times
    Pastore, Erica
    Alfieri, Arianna
    Castiglione, Claudio
    Nicosia, Gaia
    Salassa, Fabio
    IFAC PAPERSONLINE, 2022, 55 (10): : 2167 - 2172
  • [48] The capacitated lot-sizing and scheduling problem with sequence-dependent setup costs and setup times
    Gupta, D
    Magnusson, T
    COMPUTERS & OPERATIONS RESEARCH, 2005, 32 (04) : 727 - 747
  • [49] A GENETIC ALGORITHM FOR THE UNRELATED PARALLEL MACHINE SCHEDULING PROBLEM WITH JOB SPLITTING AND SEQUENCE-DEPENDENT SETUP TIMES - LOOM SCHEDULING
    Eroglu, Duygu Yilmaz
    Ozmutlu, H. Cenk
    Koksal, Seyit Ali
    TEKSTIL VE KONFEKSIYON, 2014, 24 (01): : 66 - 73
  • [50] A cutting plane algorithm for solving single machine scheduling problems with uncertain sequence-dependent setup times
    Zegordi, S. H.
    Nikbakhsh, E.
    Modarres, M.
    PROCEEDINGS OF THE 36TH INTERNATIONAL MATADOR CONFERENCE, 2010, : 119 - 122