Data-driven project buffer sizing in critical chains

被引:8
|
作者
Li, Hongbo [1 ]
Cao, Yiwu [1 ]
Lin, Qiao [1 ]
Zhu, Hanyu [1 ]
机构
[1] Shanghai Univ, Sch Management, Shanghai 200444, Peoples R China
基金
中国国家自然科学基金;
关键词
Data-driven project buffer sizing; Critical chain; Support vector regression; Machine learning; REGRESSION;
D O I
10.1016/j.autcon.2022.104134
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In critical chain project management, the probability of timely project completion can usually be increased by setting a suitable project buffer. Existing studies tend to explicitly construct a formula to calculate the project buffer size, but there is a lack of a data-driven framework that sizes the project buffer through mining the buffer related information hidden in the project data. Therefore, from a perspective that is different from the current studies, we propose a data-driven project buffer sizing approach to size the project buffer in a prediction manner in the project planning phase. Our approach first uses a full-factor design of experiments and Monte Carlo simulation to construct the required dataset. Then, support vector regression is adopted to train the project buffer prediction model. The parameters of the support vector regression are fine-tuned via grid search and cross validation. Extensive computational experiments on the PSPLIB J30 dataset are conducted to validate our approach. Six performance measures (i.e., the mean squared error, the mean magnitude relative error, the percentage relative error deviation, the proportion of project buffer consumed, the average project buffer size and the probability of exceeding the planned duration) are employed to assess our approach. The experimental results show that our approach is competitive compared to classical project buffer sizing methods.
引用
收藏
页数:13
相关论文
共 50 条
  • [1] Buffer sizing and critical chain project management
    Transportation Development Research Center, China Academy of Transportation Science, Beijing 100029, China
    Jisuanji Jicheng Zhizao Xitong, 2008, 5 (1029-1035):
  • [2] Buffer sizing for the critical chain project management method
    Geekie, A.
    Steyn, H.
    SOUTH AFRICAN JOURNAL OF INDUSTRIAL ENGINEERING, 2008, 19 (01): : 73 - 88
  • [3] Critical chain project buffer sizing based on resource constraints
    Zhang, Junguang
    Song, Xiwei
    Diaz, Estrella
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2017, 55 (03) : 671 - 683
  • [4] Critical Chain Project Buffer Sizing Based on Capabilities Attributes
    Zhang, Junguang
    Guo, Shanshan
    ENGINEERING MANAGEMENT JOURNAL, 2025,
  • [5] Project Characteristics Based Buffer Sizing to Critical Chain Scheduling
    Guo Ze
    Zheng Zheng
    Lin ShuMin
    Yang RuiFeng
    PROCEEDINGS OF THE 31ST CHINESE CONTROL CONFERENCE, 2012, : 2400 - 2405
  • [6] Buffer sizing in critical chain project management by network decomposition *
    She, Bingling
    Chen, Bo
    Hall, Nicholas G.
    OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2021, 102
  • [7] Buffer Sizing Methods to Compare Critical Chain Project Management with Critical Path
    Shurrab, Mohammed
    Abbasi, Ghaleb
    INTERNATIONAL JOURNAL OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT, 2016, 7 (03) : 74 - 87
  • [8] Incorporation of resource reliability into critical chain project management buffer sizing
    Zarghami, Seyed Ashkan
    Gunawan, Indra
    de Zubielqui, Graciela Corral
    Baroudi, Bassam
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2020, 58 (20) : 6130 - 6144
  • [9] Buffer Sizing in Critical Chain Project Management by Brittle Risk Entropy
    Peng, Jun-long
    Peng, Chao
    BUILDINGS, 2022, 12 (09)
  • [10] Project buffer sizing of a critical chain based on comprehensive resource tightness
    Zhang, Junguang
    Song, Xiwei
    Diaz, Estrella
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2016, 248 (01) : 174 - 182