Revisiting critical delay factors for construction: Analysing projects in Malaysia

被引:58
|
作者
Yap, Jeffrey Boon Hui [1 ]
Goay, Pei Ling [1 ]
Woon, Yoke Bee [1 ]
Skitmore, Martin [2 ]
机构
[1] Univ Tunku Abdul Rahman, Lee Kong Chian Fac Engn & Sci, Sungai Long Campus, Kajang 43000, Malaysia
[2] Queensland Univ Technol, Sch Built Environm, Fac Sci & Engn, Brisbane, Qld, Australia
关键词
Construction industry; Developing countries; Project management; Schedule delays; Delay factors; CRITICAL SUCCESS FACTORS; COST OVERRUNS; CAUSATIVE FACTORS; FAILURE FACTORS; DESIGN CHANGES; MANAGEMENT; TIME; MITIGATION; RANKING;
D O I
10.1016/j.aej.2020.11.021
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Although construction delays have been subjected to a considerable amount of research, this perennial problem continues to plague the construction industry globally. For this reason, this study contributes to the theory and practice of construction schedule management by identifying the primary delay causes of construction projects and uncovering the underlying factors involved. Following a meta-analysis of 52 common causes of delay identified from the literature review, 20 highly-cited causes are categorised under client-, contractor-, consultant-, labour and equipment-, material- and others-related. A field survey was employed to acquire the views of 148 Malaysian construction practitioners from client, consultant and contractor organisations. These causes are prioritised according to an importance index that integrates both frequency and severity indices, identifying the five leading causes as lack of proper planning and scheduling, too many change orders by clients, lack of competent site management and supervision, lack of competent subcontractors and financial problems of contractors. Spearman's rank correlation tests reveal a good consensus between the respondent groups to further corroborate the findings. A factor analysis identifies the five principal managerial capabilities influencing schedule delays to be competency management, communication and coordination management, financial management, risk management and site management. These findings are helpful for the praxis of critical reflection in the planning and management of production in construction. This study provides the international construction community with valuable insights to revaluate delay factors and realign project management strategies to ensure the timely delivery of projects. (C) 2020 The Authors. Published by Elsevier B.V. on behalf of Faculty of Engineering, Alexandria University.
引用
收藏
页码:1717 / 1729
页数:13
相关论文
共 50 条
  • [31] Critical Success Factors for Different Components of Construction Projects
    Kog, Yue Choong
    Loh, Ping Kit
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2012, 138 (04): : 520 - 528
  • [32] Exploring the critical waste factors affecting construction projects
    Bajjou, Mohamed Saad
    Chafi, Anas
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2022, 29 (06) : 2268 - 2299
  • [33] Critical Success Factors of the Briefing Process for Construction Projects
    Yu, Ann T. W.
    Shen, Geoffrey Q. P.
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (03)
  • [34] Significant factors causing cost overruns in large construction projects in Malaysia
    Memon, A. H., 1600, Asian Network for Scientific Information (13):
  • [35] Extraction of underlying factors causing construction projects delay in Nigeria
    Egwim, Christian Nnaemeka
    Alaka, Hafiz
    Toriola-Coker, Luqman Olalekan
    Balogun, Habeeb
    Ajayi, Saheed
    Oseghale, Raphael
    JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2023, 21 (05) : 1323 - 1342
  • [36] MANAGING CONSTRUCTION PROJECTS: A COMPARATIVE ANALYSIS OF SUCCESS FACTORS IN POLAND AND MALAYSIA
    Dziekonski, Krzysztof
    AKTUALNE PROBLEMY PODNIKOVEJ SFERY 2015, 2015, : 80 - 87
  • [37] Ranking of delay factors in construction projects after Egyptian revolution
    Aziz, Remon Fayek
    ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (03) : 387 - 406
  • [38] The Investigation of the Role of RFID in Mitigating Delay Factors in Construction Projects
    Azeez, Luqman Ibrahim
    Radmehr, Mehrshad
    TEHNICKI VJESNIK-TECHNICAL GAZETTE, 2022, 29 (03): : 933 - 942
  • [39] Critical path effect based delay analysis method for construction projects
    Yang, Jyh-Bin
    Kao, Chih-Kuei
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (03) : 385 - 397
  • [40] The performance of construction partnering projects in Malaysia
    Ali, Azlan-Shah
    Mohd-Don, Zuraidah
    Alias, Anuar
    Kamaruzzaman, Syahrul-Nizam
    Pitt, Michael
    INTERNATIONAL JOURNAL OF THE PHYSICAL SCIENCES, 2010, 5 (04): : 327 - 333