Project Hydropower Plant "Iller Au" - An Ecological Compatible Hydropower Plant with Dynamic Regulation of Operation Water Level

被引:0
|
作者
Fessler, Walter [1 ]
Wiegand, Volker [1 ]
Brennauer, Bernd [1 ]
Schuchert, Michael [2 ]
机构
[1] Allgauer Uberlandwerk GmbH AUW, Illerstr 18, D-87435 Kempten, Germany
[2] Ingenieurbiko Dr Ing Koch Bauplanung GmbH, Beethovenstr 13, D-87435 Kempten, Germany
关键词
D O I
暂无
中图分类号
TV21 [水资源调查与水利规划];
学科分类号
081501 ;
摘要
The article reports about the project development process to the point of the initial operation of a VLH-turbine with two rubber dams including an outlet-dependency on the regulation of operation water level. The characteristic of this power plant, situated on the river Iller in Sulzberg near Kempten, is a low head between 1.4 and 2.3 m as well as the local conditions. The use of the VLH-technique in a mountain river and in combination with a dynamic regulation of retention water level elevation is so far unique. To improve the annual output of approximately 3.9 million kWh/a, the retention water level elevation will be triggered for a defined schedule and therefore the ecological changes of the aquatic ecology will be minimized. The realization of this project supports the strategy of the Bavarian government in a program for small power plants with an installed capacity < 1 MW. In this context the Bavarian government focuses also on innovative concepts of water power plants, which represent a special water-compatible kind of water power as "ecological water power stations". For realization of this project a joint company, the Illerkraftwerk Au GmbH was established by AUW and the Bavarian Landeswasserkraftwerke GmbH.
引用
下载
收藏
页码:55 / 61
页数:7
相关论文
共 50 条
  • [1] Hydropower plant "Iller Au" - An ecological compatible hydropower plant
    Schuchert, Michael
    WASSERWIRTSCHAFT, 2017, 107 (10) : 50 - 53
  • [2] Water level oscillations in reservoir caused by upstream hydropower plant operation
    Muskatirovic, J
    Kapor, R
    HYDRAULIC ENGINEERING SOFTWARE VI, 1996, : 243 - 248
  • [3] AGC strategy of hydropower plant considering regulation performance and economy of hydropower plant
    Li B.
    Mai Z.
    Dianli Zidonghua Shebei/Electric Power Automation Equipment, 2023, 43 (01): : 107 - 112and139
  • [4] WATER-LEVEL CONTROL IN HYDROPOWER PLANT - CLOSURE
    JIMENEZ, OF
    CHAUDHRY, MH
    JOURNAL OF ENERGY ENGINEERING-ASCE, 1994, 120 (02): : 100 - 101
  • [5] Operation and Maintenance of the Merowe Hydropower Plant
    Brown, Martin
    Scheid, Yannick
    Moedinger, Jens
    WASSERWIRTSCHAFT, 2011, 101 (1-2) : 49 - 53
  • [6] Commissioning and Operation of the Hydropower Plant Rheinfelden
    Ficht, Stefan
    WASSERWIRTSCHAFT, 2013, 103 (06) : 35 - 37
  • [7] Dynamic Model of a Small Hydropower Plant
    Jaliu, C.
    Visa, I.
    Diaconescu, D.
    Saulescu, R.
    Neagoe, M.
    Climescu, O.
    OPTIM 2010: PROCEEDINGS OF THE 12TH INTERNATIONAL CONFERENCE ON OPTIMIZATION OF ELECTRICAL AND ELECTRONIC EQUIPMENT, PTS I-IV, 2010, : 1216 - 1223
  • [8] Peak hydropower plant operation based on stochastic dynamic programming analysis
    Tică, Eliza–Isabela
    Popa, Radu
    UPB Scientific Bulletin, Series D: Mechanical Engineering, 2016, 78 (04): : 191 - 206
  • [9] Water level control of a small hydropower plant with a surge tank
    Borkowski, Dariusz
    JOURNAL OF HYDRAULIC RESEARCH, 2017, 55 (02) : 284 - 291
  • [10] Automated operation of the Rhine hydropower plant Sackingen
    Mergner, Volker
    WASSERWIRTSCHAFT, 2008, 98 (06) : 29 - 31