A Heuristic Algorithm for Solving Multi-crane Scheduling Problem in Batch Annealing Process

被引:1
|
作者
Xie, Xie [1 ]
Kong, Xiangyu [1 ]
Zheng, Yongyue [2 ]
Wei, Kun [1 ]
机构
[1] Shenyang Univ, Key Lab Mfg Ind & Integrated Automat, Shenyang, Peoples R China
[2] Liaoning Inst standardizat, Shenyang, Peoples R China
基金
中国国家自然科学基金;
关键词
Batch annealing process; Crane scheduling; Heuristic algorithm; Absolute performance analysis;
D O I
10.4028/www.scientific.net/AMM.620.179
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper investigates the scheduling of the multi-crane operations in batch annealing process in an iron and steel enterprise so that the completion time of the last annealed coil (makespan) is minimized. The annealing process of each coil consists of two-stage: heating and cooling. To start heating (cooling) for each coil, a special machine named furnace (cooler) must be loaded on. Once the heating (cooling) is completed, the furnace (cooler) must be unloaded immediately without any delay by crane (job no-wait constraint). The aim of our studied problem is to schedule finite machines (furnaces and coolers) by cranes to process jobs under the consideration for avoiding collision between two adjacent cranes and satisfying job no-wait constraint. For solving the problem, we present a heuristic algorithm combining earliest job requirement and closest crane first. Through the theoretical analysis, we show the absolute performance bound of the proposed heuristic algorithm.
引用
收藏
页码:179 / +
页数:2
相关论文
共 50 条
  • [41] A Heuristic Algorithm for Solving the Aircraft Landing Scheduling Problem with a Landing Sequence Division
    Shi, Wen
    Jiang, Shan
    Liang, Xuan
    Zhou, Na
    IEICE TRANSACTIONS ON FUNDAMENTALS OF ELECTRONICS COMMUNICATIONS AND COMPUTER SCIENCES, 2019, E102A (08) : 966 - 973
  • [42] A heuristic algorithm for solving hybrid flow-shop master scheduling problem
    Chen Zhumin
    PROCEEDINGS OF 2009 INTERNATIONAL CONFERENCE OF MANAGEMENT SCIENCE AND INFORMATION SYSTEM, VOLS 1-4, 2009, : 247 - 251
  • [43] A meta-heuristic method for solving scheduling problem: crow search algorithm
    Adhi, Antono
    Santosa, Budi
    Siswanto, Nurhadi
    INTERNATIONAL CONFERENCE ON INDUSTRIAL AND SYSTEMS ENGINEERING (ICONISE) 2017, 2018, 337
  • [44] Scheduling Model and Heuristic Algorithm for Roller Annealing
    Song, Jiwei
    Tang, Jiafu
    Luo, Xinggang
    Liu, Shu'an
    2008 CHINESE CONTROL AND DECISION CONFERENCE, VOLS 1-11, 2008, : 1052 - 1055
  • [45] Heuristic method for solving PDP scheduling problem
    Lu, Rui
    Wang, Cheng-En
    Dongbei Daxue Xuebao/Journal of Northeastern University, 2009, 30 (05): : 628 - 631
  • [46] A Novel Fast Parallel Batch Scheduling Algorithm for Solving the Independent Job Problem
    Zhang, Bin
    Wu, Dawei
    Song, Yingjie
    Liu, Kewei
    Xiong, Juxia
    APPLIED SCIENCES-BASEL, 2020, 10 (02):
  • [47] A Heuristic Batch Flow Line Dynamic Scheduling Algorithm for the Job-Shop Problem
    Peng, Wen-feng
    Du, Zhong-jun
    Wen, Yu
    INTERNATIONAL CONFERENCE ON INFORMATION TECHNOLOGY AND MANAGEMENT ENGINEERING (ITME 2014), 2014, : 111 - 116
  • [48] Hybrid Imperialist Competitive Algorithm for Solving Multi-Factory Integrated Scheduling Problem with Multi-Trip Batch Delivery
    Tang J.-K.
    Hu R.
    Qian B.
    Jin H.-P.
    Xiang F.-H.
    Tien Tzu Hsueh Pao/Acta Electronica Sinica, 2022, 50 (07): : 1621 - 1630
  • [49] A multi-vessel quay crane assignment and scheduling problem: Formulation and heuristic solution approach
    Fu, Yi-Min
    Diabat, Ali
    Tsai, I-Tsung
    EXPERT SYSTEMS WITH APPLICATIONS, 2014, 41 (15) : 6959 - 6965
  • [50] A Heuristic Algorithm for Flowshop Scheduling Problem
    Tang, Dan
    Shu, Hong Ping
    MANUFACTURING ENGINEERING AND AUTOMATION II, PTS 1-3, 2012, 591-593 : 626 - 630