Estimation of Distribution Algorithms for the Multi-Mode Resource Constrained Project Scheduling Problem

被引:0
|
作者
Ayodele, Mayowa [1 ]
McCall, John [1 ]
Regnier-Coudert, Olivier [1 ]
机构
[1] Robert Gordon Univ, Aberdeen, Scotland
关键词
GENETIC ALGORITHM; MULTIPLE-MODES; SAT SOLVERS; RCPSP;
D O I
暂无
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Multi-Mode Resource Constrained Project Problem (MRCPSP) is a multi-component problem which combines two interacting sub-problems; activity scheduling and mode assignment. Multi-component problems have been of research interest to the evolutionary computation community as they are more complex to solve. Estimation of Distribution Algorithms (EDAs) generate solutions by sampling a probabilistic model that captures key features of good solutions. Often they can significantly improve search efficiency and solution quality. Previous research has shown that the mode assignment sub-problem can be more effectively solved with an EDA. Also, a competitive Random Key based EDA (RK-EDA) for permutation problems has recently been proposed. In this paper, activity and mode solutions are respectively generated using the RK-EDA and an integer based EDA. This approach is competitive with leading approaches of solving the MRCPSP.
引用
收藏
页码:1579 / 1586
页数:8
相关论文
共 50 条
  • [41] Modelling and Solving Multi-mode Resource-Constrained Project Scheduling
    Szeredi, Ria
    Schutt, Andreas
    [J]. PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING, CP 2016, 2016, 9892 : 483 - 492
  • [42] A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags
    Sabzehparvar, Majid
    Seyed-Hosseini, S. Mohammad
    [J]. JOURNAL OF SUPERCOMPUTING, 2008, 44 (03): : 257 - 273
  • [43] A mathematical model for the multi-mode resource-constrained project scheduling problem with mode dependent time lags
    Majid Sabzehparvar
    S. Mohammad Seyed-Hosseini
    [J]. The Journal of Supercomputing, 2008, 44 : 257 - 273
  • [44] A Benders decomposition algorithm for the multi-mode resource-constrained multi-project scheduling problem with uncertainty
    Sadeghloo, Maryam
    Emami, Saeed
    Divsalar, Ali
    [J]. ANNALS OF OPERATIONS RESEARCH, 2024, 339 (03) : 1637 - 1677
  • [45] Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem
    Kannimuthu, Marimuthu
    Raphael, Benny
    Ekambaram, Palaneeswaran
    Kuppuswamy, Ananthanarayanan
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2020, 27 (04) : 893 - 916
  • [46] A Constraint Programming Formulation of the Multi-Mode Resource-Constrained Project Scheduling Problem for the Flexible Job Shop Scheduling Problem
    Yuraszeck, Francisco
    Montero, Elizabeth
    Canut-De-Bon, Dario
    Cuneo, Nicolas
    Rojel, Maximiliano
    [J]. IEEE ACCESS, 2023, 11 : 144928 - 144938
  • [47] A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem
    Bold, Matthew
    Goerigk, Marc
    [J]. OPERATIONS RESEARCH LETTERS, 2022, 50 (05) : 581 - 587
  • [48] A Modified NSGA-II for the Multiobjective Multi-mode Resource-Constrained Project Scheduling Problem
    Vanucci, Sanderson C.
    Bicalho, Rafael
    Carrano, Eduardo G.
    Takahashi, Ricardo H. C.
    [J]. 2012 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC), 2012,
  • [49] Four Payment Models for the Multi-Mode Resource Constrained Project Scheduling Problem with Discounted Cash Flows
    Gündüz Ulusoy
    Funda Sivrikaya-Şerifoğlu
    Şule Şahin
    [J]. Annals of Operations Research, 2001, 102 : 237 - 261
  • [50] Multi-mode resource-constrained project scheduling problem with multiple shifts and dynamic energy prices
    Peng, Wuliang
    Yu, Dongmin
    Xie, Fang
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2024,