Construction of the 938 ha reclamation for Hong Kong's new airport at Chek Lap Kok was essentially complete in July 1995. The construction of facilities on the reclamation commenced, prior to completion of the reclamation, in November 1994 and will be complete early in 1998 in time for the airport opening. Settlement of the reclamation has been ongoing during construction of these facilities and Will continue, at a reduced rate, during the operational life of the airport, This paper briefly describes the ground conditions at the site in so far as they affect settlement. Settlement predictions based on purely analytical methods using parameters derived from laboratory and in situ testing are discussed. A more reliable 'observational' prediction method which makes full use of the monitoring data is described and estimates of the residual settlement of the reclamation are given, The paper then describes the factors which result in significant variability of the settlement profile over relatively short distances and examples of this variability are given. Finally, the implications of the settlement on the design of the airport are briefly discussed.
引用
收藏
页码:191 / +
页数:31
相关论文
共 50 条
  • [11] The new Hong Kong international airport fiasco: accountability failure and the limits of the new managerialism
    Lee, EWY
    INTERNATIONAL REVIEW OF ADMINISTRATIVE SCIENCES, 2000, 66 (01) : 57 - 72
  • [12] A test of visibility sensors at Hong Kong International Airport
    Chan, P. W.
    WEATHER, 2016, 71 (10) : 241 - 246
  • [13] Hong Kong International Airport - civil engineering design
    Plant, G.W.
    Oakervee, D.E.
    Proceedings of the Institution of Civil Engineers: Civil Engineering, 1998, 126 (Special Issu): : 15 - 34
  • [14] Measles outbreak at an international airport: a Hong Kong perspective
    Hon, K. L.
    Leung, Alexander K. C.
    Leung, Karen
    Chan, Godfrey C. F.
    HONG KONG MEDICAL JOURNAL, 2019, 25 (04) : 331 - 333
  • [15] Hong Kong International Airport - civil engineering design
    Plant, GW
    Oakervee, DE
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 1998, 126 : 15 - 34
  • [16] Aerosol characteristics at the Hong Kong International Airport in 2003
    Cheng, AYS
    Walton, A
    Chan, RLM
    Lee, OSM
    Optical Technologies for Atmospheric, Ocean, and Environmental Studies, Pts 1 and 2, 2005, 5832 : 164 - 171
  • [17] Wayfinding in the passenger terminal of Hong Kong International Airport
    Lam, WHK
    Tam, ML
    Wong, SC
    Wirasinghe, SC
    JOURNAL OF AIR TRANSPORT MANAGEMENT, 2003, 9 (02) : 73 - 81
  • [18] Land Reclamation and Settlement of Reclaimed Land for New Ports
    Leung, Chun F.
    Lam, James P. W.
    Salim, El F.
    Chian, Siau C.
    PORTS 2019: PORT ENGINEERING, 2019, : 284 - 294
  • [19] InSAR detection of residual settlement of an ocean reclamation engineering project: a case study of Hong Kong International Airport
    Qing Zhao
    Hui Lin
    Wei Gao
    Howard A. Zebker
    Albert Chen
    Kin Yeung
    Journal of Oceanography, 2011, 67 : 415 - 426
  • [20] InSAR detection of residual settlement of an ocean reclamation engineering project: a case study of Hong Kong International Airport
    Zhao, Qing
    Lin, Hui
    Gao, Wei
    Zebker, Howard A.
    Chen, Albert
    Yeung, Kin
    JOURNAL OF OCEANOGRAPHY, 2011, 67 (04) : 415 - 426