Bridge construction progress monitoring using lidar and 4D design models

被引:56
|
作者
Puri, Nisha [1 ]
Turkan, Yelda [1 ]
机构
[1] Oregon State Univ, Sch Civil & Construct Engn, Corvallis, OR 97331 USA
关键词
Progress tracking; Bridge construction; Percentage of completion (POC); Incremental progress tracking; Mobile laser scanning; Lidar; 4D design models; COST OVERRUNS; MANAGEMENT; TIME;
D O I
10.1016/j.autcon.2019.102961
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Accurate data collected from on-going construction projects assists project field engineers with tracking the progress of construction work. The comparison of as-planned schedules against the as-built status of construction enables the involved parties to determine project performance. Periodic monitoring of project performance enables timely identification of discrepancies between the schedule baseline and the project schedule. The rapid identification of discrepancies allows necessary measures to be taken to minimize the impact of a delay on the construction workflow. In transportation projects, the traditional means of acquiring as-built data from a construction site prevents involved parties from receiving the required information from the site in a timely manner. The delay in the communication of information ultimately causes subsequent delays in implementing necessary courses of action targeted toward improving the workflow. Therefore, this project develops a technology-supplemented progress monitoring approach. The approach implements as-built data with a high level of detail is obtained from a jobsite within a reasonable period of time using lidar technology while ensuring the safety of the data collector. The proposed framework utilizes point cloud data obtained using mobile lidar technology and 4D design models to identify deviations of the performed work from the planned work. The framework was tested using as-built data acquired from an on-going bridge construction project, and Percentage of Completion (POC) for the as-built bridge elements are calculated and compared with the as-planned POC. The differences between these two POC values for every element, on a particular scan date, are used for assessing the performance of the proposed framework. The obtained POC difference values ranged from 7% to 6% for most elements, which shows that the developed framework enables tracking the completion of individual bridge elements in an accurate and efficient manner.
引用
收藏
页数:15
相关论文
共 50 条
  • [1] Monitoring Construction Progress Based on 4D BIM Technology
    Chen, Jingjing
    Wu, Juan
    Qu, Yan
    [J]. 6TH INTERNATIONAL CONFERENCE ON ENVIRONMENTAL SCIENCE AND CIVIL ENGINEERING, 2020, 455
  • [2] Bridge Construction Monitoring Using LiDAR Data
    Yuan, Xinxing
    Moreu, Fernando
    Lippitt, Christopher D.
    [J]. TRAN-SET 2021: PROCEEDINGS OF THE TRAN-SET CONFERENCE 2021, 2021, : 317 - 323
  • [3] 4D BIM model adaptation based on construction progress monitoring
    Sigalov, K.
    Koenig, M.
    [J]. EWORK AND EBUSINESS IN ARCHITECTURE, ENGINEERING AND CONSTRUCTION, 2018, : 337 - 344
  • [4] Acquisition and Consecutive Registration of Photogrammetric Point Clouds for Construction Progress Monitoring Using a 4D BIM
    Tuttas, Sebastian
    Braun, Alexander
    Borrmann, Andre
    Stilla, Uwe
    [J]. PFG-JOURNAL OF PHOTOGRAMMETRY REMOTE SENSING AND GEOINFORMATION SCIENCE, 2017, 85 (01): : 3 - 15
  • [5] Acquisition and Consecutive Registration of Photogrammetric Point Clouds for Construction Progress Monitoring Using a 4D BIM
    Sebastian Tuttas
    Alexander Braun
    André Borrmann
    Uwe Stilla
    [J]. PFG – Journal of Photogrammetry, Remote Sensing and Geoinformation Science, 2017, 85 : 3 - 15
  • [6] 4D CAD model updating using image processing-based construction progress monitoring
    Kim, Changyoon
    Kim, Byoungil
    Kim, Hyoungkwan
    [J]. AUTOMATION IN CONSTRUCTION, 2013, 35 : 44 - 52
  • [7] Visualization of Construction Progress Monitoring with 4D Simulation Model Overlaid on Time-Lapsed Photographs
    Golparvar-Fard, Mani
    Pena-Mora, Feniosky
    Arboleda, Carlos A.
    Lee, SangHyun
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2009, 23 (06) : 391 - 404
  • [8] Construction Progress Monitoring through the Integration of 4D BIM and SLAM-Based Mapping Devices
    Vassena, Giorgio P. M.
    Perfetti, Luca
    Comai, Sara
    Ventura, Silvia Mastrolembo
    Ciribini, Angelo L. C.
    [J]. BUILDINGS, 2023, 13 (10)
  • [9] Using 4D BIM to assess construction risks during the design phase
    Jin, Ziyu
    Gambatese, John
    Liu, Ding
    Dharmapalan, Vineeth
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2019, 26 (11) : 2637 - 2654
  • [10] 4D model based automated construction activity monitoring
    Rebolj, D.
    Podbreznik, P.
    Babic, N. C.
    [J]. EWORK AND EBUSINESS IN ARCHITECTURE, ENGINEERING AND CONSTRUCTIO N, 2009, : 553 - 556