Cave management at Finsch Mine

被引:0
|
作者
Preece, C. A.
Liebenberg, B.
机构
[1] De Beers Finsch Mine
关键词
Caves;
D O I
暂无
中图分类号
TF [冶金工业];
学科分类号
0806 ;
摘要
Finsch Diamond Mine, part of De Beers Consolidated Mines (DBCM), is situated between Kimberley and Postmasburg in the Northern Cape, South Africa. The kimberlite pipe was discovered in 1960 and De Beers assumed full mining rights three years later. Production commenced in 1966 from an opencast mine, and the operation moved underground in 1990 by developing and implementing a new mining method of blast hole open stoping. A mechanized block cave was brought into production in 2005. While block caving was not new to DBCM, with productive caves having operated in Kimberley and Cullinan, from the outset, the Finsch caving operation was designed as the most advanced with a semi-automated ground handling system. The extraction level was laid out as a single sided herringbone system due to the very poor ground conditions on the south side of the pipe. These factors combined to create a unique environment, which necessitated a completely new approach to draw control. The required system was developed by a team consisting of DBCM personnel from head office and Finsch, GEMCOM and Sandvik-Tamrock, the equipment manufacturers. It was essential that the system could be run quickly, provide daily updates and issue calls directly to the LHDs. it was also important that the base data were obtained from the resource model, which was to be depleted on a monthly basis, thus forming a close link between mine planning and draw control. A further requirement of the system was that it would form a central database for the extraction operation where all data pertaining to delays and changes in conditions, be they production or ground condition related, could be recorded and analysed. The design brought together empirical rules and tables developed at Cullinan plus concepts from programming developed for the front cave at Koffiefontein so that the new system was based on sound practical experience. These facets were incorporated into PCBC (GEMCOM) and CMS and PCS (Sandvik-Tamrock programmes). The system has now been operational for just under a year and while modifications have had to be made, it has proved itself as a practical and reliable tool with which to manage the draw control at Finsch. The system is unforgiving and has forced the production team to focus on the specified drawpoints. Problems have been encountered but most of these have been related to re-educating a workforce, familiar with a flexible mining method, to the strict discipline required for a modem block cave.
引用
收藏
页码:775 / 781
页数:7
相关论文
共 50 条
  • [31] Predicting gob cave by rock movement at the Quinsam Coal Mine
    Cullen, M
    Pakalnis, RC
    Payne, D
    ROCK MECHANICS TOOLS AND TECHNIQUES, VOLS 1 AND 2, 1996, : 443 - 448
  • [32] Cave mine pillar stability analysis using machine learning
    Quevedo, R. J.
    Sari, Y. A.
    McKinnon, S. D.
    JOURNAL OF THE SOUTHERN AFRICAN INSTITUTE OF MINING AND METALLURGY, 2024, 124 (02) : 43 - 52
  • [33] Indian mine cave-in kills at least 50 workers
    不详
    TCE, 2006, (784): : 11 - 11
  • [34] A review - Pillar stability issues at DOZ block cave mine
    Sinuhaji, A.
    Flint, D.
    Rindriatmoko, O.
    9th AusIMM Underground Operators Conference 2005, 2005, 2005 (01): : 359 - 362
  • [35] Scale model investigation of ventilation parameters in a block cave mine
    Jha, A.
    Pan, Y.
    Tukkaraja, P.
    Sridharan, S. J.
    MINE VENTILATION, NAMVS 2021, 2021, : 556 - 562
  • [36] Interaction between the block cave and the pit slopes at Palabora mine
    Moss, A.
    Diachenko, S.
    Townsend, P.
    JOURNAL OF THE SOUTHERN AFRICAN INSTITUTE OF MINING AND METALLURGY, 2006, 106 (07) : 479 - 484
  • [37] RAPID GROWTH AND RECRYSTALLIZATION OF CAVE PEARLS IN AN UNDERGROUND LIMESTONE MINE
    Melim, Leslie A.
    Spilde, Michael N.
    JOURNAL OF SEDIMENTARY RESEARCH, 2011, 81 (11-12) : 775 - 786
  • [38] FINSCH GOES OFF WITH A BANG.
    Anon
    South African Mining and Engineering Journal, 1980, 91 (4161):
  • [39] Mined - out area exploration and treatment of Zhangjiagedan mine cave of Heidaigou Open Pit Coal Mine
    Zhao, Yin-Tao
    Cao, Yong
    Qiao, Zhi-Chun
    Meitan Xuebao/Journal of the China Coal Society, 2006, 31 (SUPPL.): : 140 - 143
  • [40] Cave fragmentation in a cave-to-mill context at the New Afton mine Part II: implications to mill performance
    Nadolski, Stefan
    O'Hara, Christopher
    Klein, Bern
    Elmo, Davide
    Hart, Craig J. R.
    MINING TECHNOLOGY-TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY, 2018, 127 (03) : 155 - 166