Theoretical and practical fundamentals for multi-objective optimisation in resource-constrained project scheduling problems

被引:38
|
作者
Ballestin, Francisco [1 ]
Blanco, Rosa [1 ]
机构
[1] Univ Publ Navarra, Dpto Estadist & Invest Operat, Fac Econ & Empresariales, Pamplona, Spain
关键词
Resource-constrained project scheduling; Multi-objective; Heuristic algorithms; GENETIC ALGORITHM; HEURISTICS;
D O I
10.1016/j.cor.2010.02.004
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Project scheduling is an inherently multi-objective problem, since managers want to finish projects as soon as possible with the minimum cost and the maximum quality. However, there are only a few papers dealing with multiobjective resource-constrained project scheduling problems (MORCPSPs). Moreover, there is no theoretical study in the literature that establishes the fundamentals for correct algorithmic developments. In this paper we try to close the gap by proving several results for MORCPSPs. With these results as a basis, both exact and heuristic procedures capable of obtaining a set of efficient solutions for several important MORCPSPs can be created. We develop algorithms for the case where all objective functions are of the same type, called regular. In this case, specific codifications, techniques, and procedures can be used. Extensive computational results help decide which algorithms or techniques are the most promising for the problem. With the aid of these algorithms we study the Pareto fronts in this case. Finally, we apply a metaheuristic algorithm to a particular example of the general case in order to analyse the differences in the Pareto fronts. The project instances and Pareto fronts obtained can be downloaded from a website to facilitate comparisons with future research efforts. (C) 2010 Elsevier Ltd. All rights reserved.
引用
收藏
页码:51 / 62
页数:12
相关论文
共 50 条
  • [1] Model Research of Multi-Objective and Resource-Constrained Project Scheduling Problem
    Zhou, Rong
    Ye, Chun-ming
    Ma, Hui-min
    [J]. 19TH INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT: MANAGEMENT SYSTEM INNOVATION, 2013, : 991 - 1001
  • [2] Multi-objective resource constrained project scheduling
    Rajagopal, K
    Rao, AR
    Muniswamy, VV
    [J]. FIRST INTERNATIONAL CONFERENCE ON OPERATIONS AND QUANTITATIVE MANAGEMENT, VOL 1 AND 2, 1997, : 119 - 126
  • [3] Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Considering Flexible Resource Profiles
    Luo, Xu
    Guo, Shunsheng
    Du, Baigang
    Luo, Xinhao
    Guo, Jun
    [J]. APPLIED SCIENCES-BASEL, 2024, 14 (05):
  • [4] Multi-objective metaheuristic algorithms for the resource-constrained project scheduling problem with precedence relations
    Gomes, Helton Cristiano
    das Neves, Francisco de Assis
    Freitas Souza, Marcone Jamilson
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2014, 44 : 92 - 104
  • [5] Optimizing multi-objective construction management for resource-constrained project scheduling problems: a bio-inspired approach
    Vu Hong Son Pham
    Loc Tin Huynh
    [J]. Asian Journal of Civil Engineering, 2024, 25 (6) : 4819 - 4837
  • [6] A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project
    Zareei, Mostafa
    Hassan-Pour, Hossein Ali
    [J]. IRANIAN JOURNAL OF MANAGEMENT STUDIES, 2015, 8 (04) : 653 - 685
  • [7] A survey in the resource-constrained project and multi-project scheduling problems
    Ben Issa, Samer
    Tu, Yiliu
    [J]. JOURNAL OF PROJECT MANAGEMENT, 2020, 5 (02) : 117 - 138
  • [8] A Practical Approach for Resource-Constrained Project Scheduling
    Manousakis, Konstantinos
    Savva, Giannis
    Papadouri, Nicos
    Mavrovouniotis, Michalis
    Christofides, Athanasios
    Kolokotroni, Nedi
    Ellinas, Georgios
    [J]. IEEE ACCESS, 2024, 12 : 12976 - 12991
  • [9] Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Problem Under Time Uncertainty
    Ghamginzadeh, Arman
    Najafi, Amir Abbas
    Khalilzadeh, Mohammad
    [J]. INTERNATIONAL JOURNAL OF FUZZY SYSTEMS, 2021, 23 (02) : 518 - 534
  • [10] Multi-Objective Multi-Skill Resource-Constrained Project Scheduling Problem Under Time Uncertainty
    Arman Ghamginzadeh
    Amir Abbas Najafi
    Mohammad Khalilzadeh
    [J]. International Journal of Fuzzy Systems, 2021, 23 : 518 - 534