Rockburst Risk Evaluation for Stage Excavation of Underground Powerhouse

被引:0
|
作者
Qiu, Dao-Hong [1 ]
Zhang, Le-Wen [1 ]
Li, Shu-Cai [1 ]
Sun, Huai-Feng [1 ]
Zhang, De-Yong [1 ]
机构
[1] Shandong Univ, Geotech & Struct Engn Res Ctr, Jinan 250061, Peoples R China
关键词
underground powerhouse; rockburst; stage excavation; numerical simulation;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The main powerhouse is the most important one for a hydropower station. It usually located in complex geological environment with high geostress. So that rockburst risk evaluation is very significant for actual construction. Stage excavation is very common in the building of underground powerhouse. It has practical significance to forecast rockburst according to the firstly excavated stage. Numerical simulations were done to analysis the distribution of the secondary stress field in order to evaluate the rockburst risk. The results show that rockburst would occur at the bottom angles of the later stage if rockburst occurred in the earlier stage, and rockburst risk of the sidewall would be weaker. Rockburst would also be weaker in the firstly excavated stage at the same time. Because of stress of the arch increased, support of the arch should be enhanced during the following construction.
引用
收藏
页码:145 / 147
页数:3
相关论文
共 50 条
  • [41] Three-dimensional elastoplastic numerical simulation of excavation and support processes for the underground powerhouse of the Shuibuya hydroelectric project
    Annan, J
    Xiating, F
    Jian, L
    Zongliang, R
    ADVANCES IN ENGINEERING PLASTICITY AND ITS APPLICATIONS, PTS 1 AND 2, 2004, 274-276 : 625 - 630
  • [42] Failure Mechanisms and Evolution Assessment of the Excavation Damaged Zones in a Large-Scale and Deeply Buried Underground Powerhouse
    Li, Hai-bo
    Liu, Ming-chang
    Xing, Wan-bo
    Shao, Shuai
    Zhou, Jia-wen
    ROCK MECHANICS AND ROCK ENGINEERING, 2017, 50 (07) : 1883 - 1900
  • [43] Discriminant Analysis of Excavation Damage Zone at Underground Powerhouse with High In-situ Ground Stresses during Construction
    DinhPhuc Hoang
    Xu, GuangLi
    Li, ZhiPeng
    Dong, JiaXing
    ELECTRONIC JOURNAL OF GEOTECHNICAL ENGINEERING, 2016, 21 (13): : 4627 - +
  • [44] Failure mechanism and mode of surrounding rock of underground powerhouse at the right bank of Wudongde hydropower station subjected to excavation
    Li A.
    Dai F.
    Xu N.
    Gu G.
    Liu K.
    Li B.
    Xu, Nuwen (xunuwen@scu.edu.cn), 2017, Academia Sinica (36): : 781 - 793
  • [45] DEWATERING FOR OPAL SPRINGS POWERHOUSE EXCAVATION.
    Schroeder, W.L.
    Rybel, Vincent W.
    Cochran, Larry
    Journal of Construction Engineering and Management, 1986, 112 (03): : 440 - 451
  • [46] Geological and Analytical Procedures for the Evaluation of Asbestos-Related Risk in Underground and Surface Rock Excavation
    Turci, Francesco
    Compagnoni, Roberto
    Piana, Fabrizio
    Delle Piane, Luca
    Tomatis, Maura
    Fubini, Bice
    Tallone, Sergio
    Fuoco, Stefano
    Bergamini, Massimo
    ENGINEERING GEOLOGY FOR SOCIETY AND TERRITORY, VOL 5: URBAN GEOLOGY, SUSTAINABLE PLANNING AND LANDSCAPE EXPLOITATION, 2015, : 619 - 622
  • [47] DEWATERING FOR OPAL-SPRINGS POWERHOUSE EXCAVATION
    SCHROEDER, WL
    RYBEL, VW
    COCHRAN, L
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03): : 440 - 451
  • [48] Rockburst risk of tunnel boring machine part-pilot excavation in very strong rockburst section of deep hard tunnel
    Xiao, Ya-Xun
    Feng, Xia-Ting
    Chen, Bing-Rui
    Feng, Guang-Liang
    Zhang, Zhao-Tai
    Ming, Hua-Jun
    Yantu Lixue/Rock and Soil Mechanics, 2011, 32 (10): : 3111 - 3118
  • [49] Rockburst risk of tunnel boring machine part-pilot excavation in very strong rockburst section of deep hard tunnel
    Xiao Ya-xun
    Feng Xia-ting
    Chen Bing-rui
    Feng Guang-liang
    Zhang Zhao-tai
    Ming Hua-jun
    ROCK AND SOIL MECHANICS, 2011, 32 (10) : 3111 - 3118
  • [50] Vibration response of large underground powerhouse
    College of Water Resources and Hydropower, Sichuan University, Chengdu 610065, China
    不详
    不详
    J Vib Shock, 9 (21-27+45):