Rockburst Risk Evaluation for Stage Excavation of Underground Powerhouse

被引:0
|
作者
Qiu, Dao-Hong [1 ]
Zhang, Le-Wen [1 ]
Li, Shu-Cai [1 ]
Sun, Huai-Feng [1 ]
Zhang, De-Yong [1 ]
机构
[1] Shandong Univ, Geotech & Struct Engn Res Ctr, Jinan 250061, Peoples R China
关键词
underground powerhouse; rockburst; stage excavation; numerical simulation;
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The main powerhouse is the most important one for a hydropower station. It usually located in complex geological environment with high geostress. So that rockburst risk evaluation is very significant for actual construction. Stage excavation is very common in the building of underground powerhouse. It has practical significance to forecast rockburst according to the firstly excavated stage. Numerical simulations were done to analysis the distribution of the secondary stress field in order to evaluate the rockburst risk. The results show that rockburst would occur at the bottom angles of the later stage if rockburst occurred in the earlier stage, and rockburst risk of the sidewall would be weaker. Rockburst would also be weaker in the firstly excavated stage at the same time. Because of stress of the arch increased, support of the arch should be enhanced during the following construction.
引用
收藏
页码:145 / 147
页数:3
相关论文
共 50 条
  • [1] EXCAVATION OF WORLDS LARGEST UNDERGROUND POWERHOUSE
    HAMEL, L
    NIXON, D
    JOURNAL OF THE CONSTRUCTION DIVISION-ASCE, 1978, 104 (03): : 333 - 351
  • [2] Preliminary study on rockburst development law and rockburst prediction in excavation of layer I of underground powerhouse system in high geostress area of Shuangjiangkou hydropower station
    Ma X.
    Li C.
    Wang X.
    Yuan G.
    Ma H.
    Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering, 2020, 39 : 2964 - 2972
  • [3] Rockburst prediction and prevention in underground space excavation
    Zhou, Jian
    Zhang, Yulin
    Li, Chuanqi
    He, Haini
    Li, Xibing
    UNDERGROUND SPACE, 2024, 14 : 70 - 98
  • [4] Acoustic emission induced by progressive excavation of an underground powerhouse
    Ishida, Tsuyoshi
    Kanagawa, Tadashi
    Uchita, Yasuo
    INTERNATIONAL JOURNAL OF ROCK MECHANICS AND MINING SCIENCES, 2014, 71 : 362 - 368
  • [6] Reinforcement with Rockbolts in Underground Powerhouse Excavation using DDA Method
    Yu, Song
    Zhu, Weishen
    Zhang, Dunfu
    ADVANCES IN CIVIL ENGINEERING, PTS 1-4, 2011, 90-93 : 2339 - +
  • [7] Research on excavation damage zone of underground powerhouse of Dagangshan hydropower station
    Zhu, Zeqi
    Sheng, Qian
    Zhang, Yonghui
    Li, Yangfan
    Zhu, Z. (zqzhu@whrsm.ac.cn), 1600, Academia Sinica (32): : 734 - 739
  • [8] Rockburst mechanism of rock mass with structural planes in underground chamber excavation
    Wu, J.
    Zhang, X. Y.
    Yu, L. Y.
    Zhang, L. W.
    Wu, T.
    ENGINEERING FAILURE ANALYSIS, 2022, 139
  • [9] Attenuation regulation of blasting vibration of underground powerhouse excavation at Zhouning Hydropower Station
    Wang, YJ
    Lang, KS
    Tian, XB
    Theory and Practice of Energetic Materials, Vol 6, 2005, : 704 - 707
  • [10] Evaluation method for potential rockburst in underground engineering
    Zhang Chuan-qing
    Yu Jin
    Chen Jun
    Lu Jing-jing
    Zhou Hui
    ROCK AND SOIL MECHANICS, 2016, 37 : 341 - 349