Technical Research on Fully-mechanized Fast Drivage for Deep Large Sections of Coal-rock Roadway in High Stress

被引:1
|
作者
Zhang, Dongsheng [1 ]
Zhang, Wei [1 ]
Wang, Xufeng [1 ]
机构
[1] China Univ Min & Technol, State Key Lab Coal Resources & Safe Min, Sch Mines, Xuzhou 221116, Jiangsu, Peoples R China
来源
关键词
Deep Coal-rock Roadway; High Stress; Large Sections; Fully-mechanized; Fast Drivage;
D O I
10.4028/www.scientific.net/AMM.94-96.1936
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Based on the achieved engineering practice results of deep roadway drivage in Xinwen Mining Area, aimed at drivage problem of deep cross-level coal-rock, EBZ-135 fully-excavating machine had been used to replace traditional roadway blasting drivage, corresponding key technology of fast supporting for deep large sections of coal-rock roadway in high stress had been proposed, and latter mating transport system transformation of fully-mechanized fast drivage technology had been cooperated, which formed a suit of fully-mechanized fast drivage technology for deep large sections of coal-rock roadway in high stress. The application results show that the fully-mechanized fast drivage technology can markedly enhance the whole shaping quality of roadway, improve drivage efficiency and cycling footage immensely, reduce roadway drivage cost, and the good result of average month footage at 300 m and maximum month footage at 360 m have been achieved finally.
引用
收藏
页码:1936 / 1940
页数:5
相关论文
共 41 条
  • [1] Fast drivage technology for large sections of deep coal-rock roadway in complicated geological conditions
    Zhang, Wei
    Zhang, Dongsheng
    Xu, Mengtang
    Electronic Journal of Geotechnical Engineering, 2013, 18 J : 1939 - 1950
  • [2] Study on deep shaft roadway fully-mechanized fast drivage packaging technology in complicated-geological conditions
    Ma Liqiang
    Zhang Dongsheng
    Zhang Wei
    Wu Xin
    Wang Xiaodong
    Zhang Weisong
    3RD INTERNATIONAL SYMPOSIUM ON MODERN MINING & SAFETY TECHNOLOGY PROCEEDINGS, 2008, : 35 - 40
  • [3] Combined test research on coal-rock pillar width setting of district sublevel for fully-mechanized face with large mining height
    Zheng, Y. F.
    Ju, W. J.
    Kang, H. P.
    ROCK CHARACTERISATION, MODELLING AND ENGINEERING DESIGN METHODS, 2013, : 889 - 894
  • [4] Coal-rock recognition method of fully-mechanized coal mining face based on improved U-net network model
    Si L.
    Wang Z.
    Xiong X.
    Tan C.
    Meitan Xuebao/Journal of the China Coal Society, 2021, 46 : 578 - 589
  • [5] Dust Simulation and Application of Forced and Exhausted Mixed Ventilation System in Half Coal-rock Fully-mechanized Excavation Face
    Zhou, Gang
    Nie, Wen
    Cheng, Weimin
    Wang, Deming
    Yu, Yanbin
    Yang, Junlei
    NATURAL RESOURCES AND SUSTAINABLE DEVELOPMENT II, PTS 1-4, 2012, 524-527 : 285 - +
  • [6] Research on technical and principle for stability of surrounding rock in deep coal roadway
    Bai, JB
    Hou, CJ
    Chen, Y
    Wang, XY
    Mining Science and Technology, 2004, : 397 - 400
  • [7] Study on Numerical Simulation of Optimization of the Width of Coal Pillar in Caving Roadway at Fully-Mechanized Caving Face of Deep Mine
    Gao Mingtao
    Zhou Ming
    PROCEEDINGS OF 2015 INTERNATIONAL SYMPOSIUM - SAFETY AND HIGH EFFICIENCY MINING IN COAL, 2015, : 63 - 70
  • [8] Influence study on rock pressure of the len th of fully-mechanized coal face with large mining height
    Kang Quanyu
    Hu Qing
    Wang Yunlong
    Progress in Mining Science and Safety Technology, Pts A and B, 2007, : 341 - 346
  • [9] Study on Filling Cross-Roadway in Fully-Mechanized Coal Faces with High Water-Content Material
    周华强
    王光伟
    雷文成
    李峰
    曲庆贺
    International Journal of Mining Science and Technology, 2001, (02) : 20 - 24
  • [10] Analysis on rock burst danger when fully-mechanized caving coal face passed fault with deep mining
    Chen Xuehua
    Li Weiqing
    Yan Xianyang
    SAFETY SCIENCE, 2012, 50 (04) : 645 - 648