Application of Grouting the Sea-Crossing Bridge foundation in the Busan-Geoje Fixed Link

被引:0
|
作者
Jeong, Gyeong-Hwan [1 ]
Park, Chan-Woo [1 ]
Kwon, Jin-Wook [1 ]
Kim, Jae-Hwan [1 ]
Kim, Chang Hwan
Jeong, Sang-Kyoon
机构
[1] Dong A Geol Engn Co, Pusan, South Korea
关键词
Full-scale field test; Caisson Foundation; Mortar grout; Self-Leveling; Monitoring System;
D O I
暂无
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
During construction of a sea-crossing bridge grouting was used to fill densely the space between the bottom of caisson and the ground. This grout mixture was mixed with anti-washout admixture after locating accurately the pre-cast caisson on three concrete landing pads. This method differs significantly from the costly conventional method, for bridge foundations offshore, where concrete is placed in situ after excavating inside of a temporary concrete coffering wall. To verify the grouting method in advance, the full-scale field tests were performed twice on land. After identifying the fluidity of the grout material to be filled, finding some possible problems with the main construction and revising the original design, the main construction has been continuing successfully with 20 caissons completed to date. The purpose of this paper is to introduce for the first time in Korea the grouting method including the automatic and the manual monitoring system based on the main construction of the caisson foundation. This method is expected to be used in the near future for a similar construction projects.
引用
收藏
页码:641 / +
页数:2
相关论文
共 50 条
  • [1] The Immersed Tunnel and Bridges of Busan-Geoje Fixed Link
    Jeong, Sangkyoon
    Kim, Jechun
    [J]. STRUCTURAL ENGINEERING INTERNATIONAL, 2012, 22 (01) : 20 - 25
  • [2] Design and construction of Busan-Geoje fixed link, S. Korea
    Yeoward, A.
    Koo, I. S.
    Fraser, D.
    [J]. PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-BRIDGE ENGINEERING, 2010, 163 (02) : 59 - 66
  • [3] Busan Geoje Fixed Link
    van Westendorp, Peter
    Louis, Bard
    Jackson, Peter
    [J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2022, 122
  • [4] Reliability-based durability design and quality control of long span bridge of Busan-Geoje Fixed Link project in Korea
    Kim, S.
    Jeong, S.
    Kim, J.
    Koo, I.
    [J]. BRIDGE MAINTENANCE, SAFETY, MANAGEMENT AND LIFE-CYCLE OPTIMIZATION, 2010, : 1823 - 1829
  • [5] ANALYSIS OF THE TUNNEL IMMERSION FOR THE BUSAN-GEOJE FIXED LINK PROJECT THROUGH SCALE MODEL TESTS AND COMPUTER SIMULATIONS
    Cozijn, Hans
    Heo, Jin Wook
    [J]. OMAE 2009, VOL 1: OFFSHORE TECHNOLOGY, 2009, : 375 - 384
  • [6] Technique of fixed time closure for main bridge of south bridge of Xiazhang Sea-Crossing Bridge
    Yi, Yun-Kun
    Xie, Ze-Fu
    Niu, Hai-Xi
    [J]. Bridge Construction, 2013, 43 (02) : 105 - 109
  • [7] Dynamic Simulation of Immersion of Tunnel Elements for Busan - Geoje Fixed Link Project
    Chakrabarti, Partha
    Chakrabarti, Subrata K.
    Olsen, Tommy
    Sig, Koo Im
    Whan, Kim Chang
    Wook, Huh Jin
    [J]. PROCEEDINGS OF THE 27TH INTERNATIONAL CONFERENCE ON OFFSHORE MECHANICS AND ARCHTIC ENGINEERING - 2008, VOL 4, 2008, : 645 - 661
  • [8] Pile Foundation Design of Sea-crossing Bridge Pier Based on Radom Wave Theory
    Yuan Wei-guo
    Liu Mu-yu
    Sun Xiang-dong
    [J]. 2010 INTERNATIONAL CONFERENCE ON ENGINEERING COMPUTATION (ICEC 2010), 2010, : 172 - 175
  • [9] Key Design Technique for Haiwen Sea-Crossing Bridge
    海文跨海大桥设计关键技术
    [J]. 1600, Wuhan Bridge Research Institute (50): : 73 - 79
  • [10] Study on the overall scheme and isolation of the main Bridge of a sea-crossing bridge
    Liang X.
    Li Q.
    Su C.
    [J]. Zhendong yu Chongji/Journal of Vibration and Shock, 2019, 38 (09): : 252 - 259and284