Causes of Delay in Building Construction Projects in Egypt

被引:243
|
作者
El-Razek, M. E. Abd [1 ]
Bassioni, H. A. [1 ]
Mobarak, A. M. [2 ]
机构
[1] Arab Acad Sci Technol & Maritime Transport, Coll Engn & Technol, Construct & Bldg Engn Dept, Alexandria 21532, Egypt
[2] DEPA United Grp, Cairo, Egypt
关键词
Buildings; Construction management; Delay time; Egypt;
D O I
10.1061/(ASCE)0733-9364(2008)134:11(831)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Delay in construction projects is considered one of the most common problems causing a multitude of negative effects on the project and its participating parties. This paper aims to identify the main causes of delay in construction projects in Egypt from the point of view of contractors, consultants, and owners. A literature review was conducted to compile a list of delay causes that was purged based on appropriateness to Egypt in seven semistructured interviews. The resulting list of delay causes was subjected to a questionnaire survey for quantitative confirmation and identification of the most important causes of delay. The overall results indicated that the most important causes are: financing by contractor during construction, delays in contractor's payment by owner, design changes by owner or his agent during construction, partial payments during construction, and nonutilization of professional construction/contractual management. The contractor and owner were found to have opposing views, mostly blaming one another for delays, while the consultant was seen as having a more intermediate view. Results' analyses suggest that in order to significantly reduce delay a joint effort based on teamwork is required. Furthermore, causes of project delay were discussed based on the type and size of the project.
引用
收藏
页码:831 / 841
页数:11
相关论文
共 50 条
  • [41] Causes and Mitigation Strategies of Delay in Power Construction Projects: Gaps between Owners and Contractors in Successful and Unsuccessful Projects
    Banobi, Edwin Thomas
    Jung, Wooyong
    [J]. SUSTAINABILITY, 2019, 11 (21)
  • [42] Virtual building for construction projects
    Sheppard, LM
    [J]. IEEE COMPUTER GRAPHICS AND APPLICATIONS, 2004, 24 (01) : 6 - 12
  • [43] Building trust in construction projects
    Khalfan, Malik M. A.
    McDermott, Peter
    Swan, Will
    [J]. SUPPLY CHAIN MANAGEMENT-AN INTERNATIONAL JOURNAL, 2007, 12 (06) : 385 - 391
  • [44] Cranes for building construction projects
    Shapira, Aviad
    Lucko, Gunnar
    Schexnayder, Clifford J.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2007, 133 (09) : 690 - 700
  • [45] Causes of cost overruns in building construction projects in Asian countries; Iran as a case study
    Amini, Shima
    Rezvani, Alireza
    Tabassi, Mohsen
    Sadati, Seyed Saeed Malek
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023, 30 (07) : 2739 - 2766
  • [46] Exploring the Causes of Design Changes in Building Construction Projects: An Interpretive Structural Modeling Approach
    Shoar, Shahab
    Chileshe, Nicholas
    [J]. SUSTAINABILITY, 2021, 13 (17)
  • [47] REDUCING REINFORCED CONCRETE MATERIALS WASTE IN CONSTRUCTION PROJECTS USING BUILDING INFORMATION MODELING IN EGYPT
    Hosny, Suad
    Ibrahim, Ahmed Hussein
    Nabil, Yasmin
    [J]. JOURNAL OF INFORMATION TECHNOLOGY IN CONSTRUCTION, 2023, 28 : 332 - 345
  • [48] Timber Construction: Construction - Building Physics - Projects
    Lueckmann, Rudolf
    [J]. BAUTECHNIK, 2022, 99 (08) : 614 - 614
  • [49] CAUSES AND EFFECTS OF VARIATIONS ON CONSTRUCTION PROJECTS
    Jayawardena, Nishadi
    Ramachandra, Thanuja
    Rotimi, James
    [J]. SUSTAINABLE SOLUTIONS IN STRUCTURAL ENGINEERING AND CONSTRUCTION, 2014, : 483 - 488
  • [50] CAUSES OF DELAYS IN IRANIAN CONSTRUCTION PROJECTS
    Khoshgoftar, Mohammad
    Abu Bakar, Abu Hassan
    Osman, Omar
    [J]. INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2010, 10 (02) : 53 - 69