Two-stage assembly flow-shop scheduling problem with non-identical assembly machines considering setup times

被引:54
|
作者
Mozdgir, A. [1 ]
Ghomi, S. M. T. Fatemi [2 ]
Jolai, F. [3 ]
Navaei, J. [2 ,4 ]
机构
[1] Payame Noor Univ, Tehran 193954697, Iran
[2] Amirkabir Univ Technol, Dept Ind Engn, Tehran, Iran
[3] Univ Tehran, Dept Ind Engn, Coll Engn, Tehran, Iran
[4] Univ Windsor, Dept Ind & Mfg Syst Engn, Windsor, ON N9B 3P4, Canada
关键词
assembly flow-shop; non-identical assembly machines; sequence dependent setup time; mathematical model; hybrid VNS heuristic; MINIMIZING MAKESPAN; BOUND ALGORITHM; COMPLETION-TIME; HEURISTICS; BICRITERIA; SEARCH;
D O I
10.1080/00207543.2012.756151
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In this paper, we address the two stage assembly flow-shop problem with multiple non-identical assembly machines in stage two to minimise weighted sum of makespan and mean completion time. Also, sequence dependent setup times are considered for the first stage. This problem is a generalisation of previously proposed two stage assembly flow-shop problems (TSAFSP). In many real world industrial and production systems, there is more than one assembly machine to assemble job components. After extending a mathematical mixed-integer linear programming model to solve the problem, we use GAMS software. The TSAFSP has been known as NP-hard. Therefore, our more general problem is NP-hard too and so for large sized problems the right way to proceed is with the use of heuristic algorithms. So in this paper a hybrid VNS heuristic, which is a combination of the variable neighbourhood search (VNS) algorithm and a novel heuristic is developed and its solutions compared with solutions obtained by GAMS. Computational experiments reveal that the hybrid VNS heuristic performs much better than GAMS with respect to the percentage errors and run times.
引用
收藏
页码:3625 / 3642
页数:18
相关论文
共 50 条
  • [1] Two-stage flow-shop scheduling problem with non-identical second stage assembly machines
    Navaei, J.
    Ghomi, S. M. T. Fatemi
    Jolai, F.
    Shiraqai, M. E.
    Hidaji, H.
    [J]. INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 69 (9-12): : 2215 - 2226
  • [2] Two-stage flow-shop scheduling problem with non-identical second stage assembly machines
    J. Navaei
    S. M. T. Fatemi Ghomi
    F. Jolai
    M. E. Shiraqai
    H. Hidaji
    [J]. The International Journal of Advanced Manufacturing Technology, 2013, 69 : 2215 - 2226
  • [4] Heuristics for an assembly flow-shop with non-identical assembly machines and sequence dependent setup times to minimize sum of holding and delay costs
    Navaei, Javad
    Ghomi, Seyyed Mohammad Taghi Fatemi
    Jolai, Fariborz
    Mozdgir, Ashkan
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2014, 44 : 52 - 65
  • [5] THE TWO-STAGE ASSEMBLY FLOWSHOP SCHEDULING PROBLEM WITH SETUP TIMES
    Allahverdi, All
    Al-Anzi, Fawaz S.
    [J]. PROCEEDINGS OF THE 38TH INTERNATIONAL CONFERENCE ON COMPUTERS AND INDUSTRIAL ENGINEERING, VOLS 1-3, 2008, : 2029 - 2035
  • [6] A competitive memetic algorithm for the distributed two-stage assembly flow-shop scheduling problem
    Deng, Jin
    Wang, Ling
    Wang, Sheng-yao
    Zheng, Xiao-long
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2016, 54 (12) : 3561 - 3577
  • [7] The two stage assembly flow-shop scheduling problem with batching and delivery
    Kazemi, Hamed
    Mazdeh, Mohammad Mahdavi
    Rostami, Mohammad
    [J]. ENGINEERING APPLICATIONS OF ARTIFICIAL INTELLIGENCE, 2017, 63 : 98 - 107
  • [8] Flow-shop scheduling with setup and assembly operations
    Yokoyama, Masao
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 187 (03) : 1184 - 1195
  • [9] A note on the two-stage assembly flow shop scheduling problem with uniform parallel machines
    Koulamas, Christos
    Kyparisis, George J.
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 182 (02) : 945 - 951
  • [10] A two-stage assembly flow-shop scheduling problem with bi-level products structure and machines' availability constraints
    Nikouei, Mohammad Ali
    Zandieh, Mostafa
    Amiri, Maghsoud
    [J]. JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2022, 39 (06) : 494 - 503