A branch and bound procedure for the resource constrained project scheduling problem with discounted cash flows

被引:73
|
作者
Icmeli, O [1 ]
Erenguc, SS [1 ]
机构
[1] UNIV FLORIDA,DEPT INFORMAT & DECIS SCI,GAINESVILLE,FL 32611
关键词
project scheduling; resource constraints; net present value;
D O I
10.1287/mnsc.42.10.1395
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Management of projects is complicated by the scarcity of resources required to execute them. Limited resources usually extend the project completion times beyond those determined by CPM/PERT. Several solution procedures have been developed for solving the resource constrained project scheduling problem. One objective commonly used for these problems is to complete the project as early as possible (minimize makespan). The problem considered in this paper is a resource constrained project scheduling problem, with the added features that there are cash flows associated with the project activities, and the objective is to schedule the project activities in such a way that the net present value of cash flows is maximized. With these features the problem becomes financially motivated and more realistic. We introduce a branch and bound procedure to solve the resource constrained project scheduling problem with discounted cash flows. Our procedure exploits the known fact that potential resource violations can be eliminated by introducing additional precedence relations between certain project activities. Specifically, we use the ''minimal delaying alternatives'' concept to resolve resource conflicts. The bounds in the branch and bound procedure are computed by solving Payment Scheduling Problems, which can be formulated as linear programs and by that are well-solvable. We test our procedure computationally on a set of 90 test problems from the literature and compare it with the only other exact procedure we know of.
引用
收藏
页码:1395 / 1408
页数:14
相关论文
共 50 条
  • [41] INSERTION ALGORITHMS TO SOLVE THE RESOURCE-CONSTRAINED MULTI-STAGE PROJECT SCHEDULING PROBLEM WITH DISCOUNTED CASH FLOW MAXIMIZATION
    Klimek, Marcin
    [J]. MANAGEMENT AND PRODUCTION ENGINEERING REVIEW, 2018, 9 (04) : 106 - 116
  • [42] Branch and Price with Constraint propagation for Resource Constrained Project Scheduling Problem
    Moukrim, Aziz
    Quilliot, Alain
    Toussaint, Helene
    [J]. 2014 INTERNATIONAL CONFERENCE ON CONTROL, DECISION AND INFORMATION TECHNOLOGIES (CODIT), 2014, : 164 - 169
  • [43] A Branch and Bound Algorithm for Project Scheduling Problem with Spatial Resource Constraints
    Hu, Shicheng
    Wang, Song
    Kao, Yonggui
    Ito, Takao
    Sun, Xuedong
    [J]. MATHEMATICAL PROBLEMS IN ENGINEERING, 2015, 2015
  • [44] A genetic algorithm for resource investment problem with discounted cash flows
    Najafi, Amir Abbas
    Niaki, Seyed Taghi A.
    [J]. APPLIED MATHEMATICS AND COMPUTATION, 2006, 183 (02) : 1057 - 1070
  • [45] Project scheduling with discounted cash flows and general. temporal constraints
    Zimmermann, J
    [J]. OPERATIONS RESEARCH PROCEEDINGS 1999, 2000, : 419 - 424
  • [46] A Logic-based Branch and Bound Algorithm for Resource Constrained Scheduling Problem
    Zhang, Juyang
    Sun, Jigui
    Yang, Qingyun
    [J]. INTERNATIONAL JOURNAL OF COMPUTER SCIENCE AND NETWORK SECURITY, 2006, 6 (2A): : 237 - 241
  • [47] A branch-and-bound algorithm for the unit-capacity resource constrained project scheduling problem with transfer times
    Liu, Ying
    Jin, Shuang
    Zhou, Jing
    Hu, Qian
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2023, 151
  • [48] A branch-and-bound algorithm for the proactive resource-constrained project scheduling problem with a robustness maximization objective
    Li, Xue
    He, Zhengwen
    Wang, Nengmin
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2024, 166
  • [49] A two-phase method for a multi-skilled project scheduling problem with discounted cash flows
    Tabrizi, B. H.
    Tavakkoli-Moghaddam, R.
    Ghaderi, S. F.
    [J]. SCIENTIA IRANICA, 2014, 21 (03) : 1083 - 1095
  • [50] MULTIPLE RESOURCE - CONSTRAINED SCHEDULING USING BRANCH AND BOUND
    STINSON, JP
    DAVIS, EW
    KHUMAWALA, BM
    [J]. AIIE TRANSACTIONS, 1978, 10 (03): : 252 - 259