Application of probabilistic cost and schedule risk assessment and risk management to large infrastructure projects

被引:0
|
作者
McGrath, T. C. [1 ]
Roberds, W. J.
Keizur, A. E.
del Olmo, A. Gutierrez [2 ]
Barbato, I. [2 ]
机构
[1] Golder Associates Inc, Redmond, WA 98052 USA
[2] Golder Associates Global Iber SL, Madrid, Spain
来源
SAFETY AND RELIABILITY FOR MANAGING RISK, VOLS 1-3 | 2006年
关键词
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Historically, engineers and planners worldwide have not adequately estimated the ultimate costs and schedules for infrastructure projects, with unidentified biases and problems sometimes causing large budget and schedule overruns. Many government agencies now recognize these issues and require probabilistic risk assessment and risk management for large projects to better estimate and control cost and schedule. Others have attempted to address these problems, but many of these attempts have significant limitations (e.g., no direct link between cost and schedule). This paper briefly describes an innovative and cost-effective approach for cost and schedule risk assessment/management and its application to a large tunnel project and a large bridge project. The approach helps mitigate historical estimating and budgeting problems by: (1) quantifying uncertainty in ultimate actual project cost and schedule within a probabilistic, risk-based, integrated cost and schedule model, in which the uncertainties in inputs are explicitly de-biased and assessed (through elicitation of technical experts) and incorporated; (2) identifying and prioritizing critical cost and schedule risks and opportunities, as well as quantifying the costs and benefits of proposed mitigation strategies to address critical risks/opportunities; and (3) improving communication and decision-making (including funding requirements).
引用
收藏
页码:2093 / +
页数:2
相关论文
共 50 条
  • [21] Qualitative assessment of risk on large projects
    Brush, D
    JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE, 2005, 131 (04) : 281 - 283
  • [22] Risk management on large capital projects
    Turnbaugh, L
    JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE, 2005, 131 (04) : 275 - 280
  • [23] Risk assessment for construction projects of transport infrastructure objects
    Titarenko, Boris
    ENERGY MANAGEMENT OF MUNICIPAL TRANSPORTATION FACILITIES AND TRANSPORT (EMMFT 2017), 2017, 90
  • [24] Is risk assessment matter in infrastructure projects on soft soils?
    Low, W. W.
    Wong, K. S.
    Lim, J. W.
    2ND INTERNATIONAL CONFERENCE ON MATERIALS TECHNOLOGY AND ENERGY, 2020, 943
  • [25] Application of probabilistic risk assessment methodology to medical risk
    Miyata, Koichi
    Furuhama, Yutaka
    Yanagawa, Tatsuo
    Abstracts of the Pacific Basin Nuclear Conference, 2004,
  • [26] Large Projects Integrators. Analysis and Management of the Data for Risk Assessment
    Demichela, Micaela
    Guarino, Mario
    Tuninetti, Giorgio
    Mancardi, Andrea
    Camuncoli, Gianfranco
    Mure, Salvine
    CISAP5: INTERNATIONAL CONFERENCE ON SAFETY & ENVIRONMENT IN PROCESS & POWER INDUSTRY, PT 1, 2012, 26 : 459 - 464
  • [27] Risk Management in Infrastructure Projects (Mypra Tunnel, Prague)
    Blindow, F.
    Padevet, M.
    Transport and City Tunnels - Proceedings of the 11th International Conference Underground Constructions Prague 2010, 2010, : 538 - 541
  • [28] Geotechnical Risk Management in Dutch Public Infrastructure Projects
    Brandsen, Cees
    Cools, Paul M. C. B. M.
    GEOTECHNICAL SAFETY AND RISK V, 2015, : 16 - 22
  • [29] Probabilistic Resilience-Guided Infrastructure Risk Management
    Salem, Shady
    Siam, Ahmad
    El-Dakhakhni, Wael
    Tait, Michael
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2020, 36 (06)
  • [30] System Dynamics Approach for Investigating the Risk Effects on Schedule Delay in Infrastructure Projects
    Wang, Jiayuan
    Yuan, Hongping
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2017, 33 (01)