Study on Schedule Control in AP1000 Nuclear Plant Project

被引:0
|
作者
Fang Xiaopeng [1 ]
机构
[1] SNPEC, Shanghai 200233, Peoples R China
关键词
Schedule Control; Modular Construction; Construction Logics;
D O I
暂无
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
The construction of AP1000 Nuclear Power Plant (NPP) has commenced in China. The AP1000 NPP features a passive design concept and modular construction technology. Based on the management of the construction of current AP1000 NNP, this paper describes the effects on Nuclear Island (NI) construction project management resulting from modular construction technology, as well as new construction techniques and methods. This paper puts forward new requirements for construction schedule management of the nuclear island construction at different levels. The AP1000 NI construction logic features the parallel construction of civil and structural erection as the main approach, with the integrated schedule of module fabrication, assembly and installation as support.
引用
收藏
页码:181 / 186
页数:6
相关论文
共 50 条
  • [21] Westinghouse AP1000 plant to load fuel
    不详
    [J]. ATW-INTERNATIONAL JOURNAL FOR NUCLEAR POWER, 2018, 63 (6-7): : 411 - 411
  • [22] Westinghouse AP1000 advanced passive plant
    Schulz, T. L.
    [J]. NUCLEAR ENGINEERING AND DESIGN, 2006, 236 (14-6) : 1547 - 1557
  • [23] AP1000
    不详
    [J]. NUCLEAR PLANT JOURNAL, 2011, 29 (02) : 10 - 10
  • [24] AP1000
    不详
    [J]. NUCLEAR PLANT JOURNAL, 2011, 29 (01) : 18 - 18
  • [25] The Usage and Research of "Potential Trend Notice" in Sanmen AP1000 Nuclear Power Plant Construction Project Change Management
    Yan, Zhaoyong
    Qian, Yongzheng
    [J]. PROCEEDINGS OF THE 20TH PACIFIC BASIN NUCLEAR CONFERENCE, VOL 1, 2017, : 955 - 964
  • [28] Control simulation and study of load rejection transient for AP1000
    Wang, Pengfei
    Chen, Zhi
    Zhang, Rui
    Sun, Jian
    He, Zhengxi
    Zhao, Fuyu
    Wei, Xinyu
    [J]. PROGRESS IN NUCLEAR ENERGY, 2015, 85 : 28 - 43
  • [29] Effectiveness analysis of hydrogen control system in AP1000 nuclear power plant under LB-LOCA
    Lyu, Xuefeng
    Cheng, Jian
    Feng, Yang
    Liu, Tianfang
    Huang, Xiong
    [J]. ANNALS OF NUCLEAR ENERGY, 2020, 147
  • [30] Analysis of passive residual heat removal system in AP1000 nuclear power plant
    Sierchula, J.
    [J]. INTERNATIONAL CONFERENCE ON THE SUSTAINABLE ENERGY AND ENVIRONMENTAL DEVELOPMENT, 2019, 214