Estimating Cost Discrepancies in Highway Contracts: Multistep Econometric Approach

被引:44
|
作者
Gkritza, Konstantina [1 ]
Labi, Samuel [2 ]
机构
[1] Iowa State Univ, Dept Civil Construct & Environm Engn, Ames, IA 50011 USA
[2] MIT, Sch Civil & Environm Engn, Cambridge, MA 02139 USA
关键词
D O I
10.1061/(ASCE)0733-9364(2008)134:12(953)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper investigates the likelihood of occurrence and quantifies the magnitude and rate of discrepancies in highway project final costs with respect to their contract award amounts. Using data from Indiana, we develop a multistep econometric approach that can be used to estimate the effects of factors associated with the contract bidding process, project type, and the project physical environment on cost discrepancies in highway contracts. Estimation findings indicate that for a given project type and project year, contracts of larger size or longer duration are generally more likely to incur cost overruns. In addition, for contracts that incur cost overruns, the cost overrun rate decreases nonlinearly with increasing contract size up to a certain point after which the cost overrun rate increases with increasing contract size. Our approach allows for the possibility that cost overrun amounts are not linearly related to contract award amounts (contract size), and shows that greater analytical flexibility needs to be incorporated into any investigation of contract cost overruns. Agencies interested in improving their financial forecasts can replicate our proposed methodology using local contract data.
引用
收藏
页码:953 / 962
页数:10