NEW INSTALLATION METHOD FOR SUBSEA PIPELINES IN SOUTH CHINA SEA

被引:0
|
作者
Chen, Chi [1 ]
Zhang, Kai [1 ]
Yang, Tianxiao [1 ]
Xiong, Ouyang [1 ]
Tang, Qian
Cheng, Yongming
机构
[1] CNOOC China Ltd Panyu Operating Co, Shenzhen 518067, Peoples R China
关键词
D O I
暂无
中图分类号
P75 [海洋工程];
学科分类号
0814 ; 081505 ; 0824 ; 082401 ;
摘要
The subsea pipelines between two platforms located in South China Sea were required to be replaced. In between the two platforms is a Floating Production Storage and Offloading (FPSO) unit including the mooring system, anchors and Pipeline End Termination (PLET). The new pipelines need to run below the FPSO and the mooring lines. This paper discusses a new installation method for the subsea pipelines in South China Sea. There are technical challenges to install the new 18-km pipelines in Panyu oil field. On the one hand, it needs to ensure a 500-m radius safety zone from the FPSO. The pipeline laying vessel shall not work within the safety zone due to possible interference with anchor lines. On the other hand, the new pipelines have to run below the FPSO and the mooring lines in order to avoid potential interference with existing cable and riser system. This paper considers the existing pipeline installation methods and generates a new method to install the pipelines in South China Sea. A concept of 'dummy pipe' is introduced to simulate the installation operation. The paper presents a series of installation sequences including assisting the pipeline laying and pulling, accurately positioning the pipelines, and protecting the existing facility. Figures are used to illustrate the installation deployment. Messenger lines were installed to run below the FPSO. The installation process was monitored. The new pipelines were installed in the field successfully. In addition, this paper further presents some recommendation for future installation practice.
引用
收藏
页码:819 / 828
页数:10
相关论文
共 50 条
  • [1] A new leak detection method for subsea pipelines
    Bai, Yong
    Zhang, Tianyu
    Li, Yanyao
    Ruan, Weidong
    Zhu, Keqiang
    SHIPS AND OFFSHORE STRUCTURES, 2017, 12 : S144 - S152
  • [2] Epifauna associated with subsea pipelines in the North Sea
    Lacey, Nichola C.
    Hayes, Peter
    ICES JOURNAL OF MARINE SCIENCE, 2020, 77 (03) : 1137 - 1147
  • [4] Research influence of hazard on the subsea pipelines in the Caspian Sea
    Fedorchuk Y.M.
    Klemeš J.J.
    Varbanov P.S.
    Matvienko V.V.
    Chemical Engineering Transactions, 2017, 61 : 1639 - 1644
  • [5] Method determines axial force in subsea pipelines
    Aynbinder, Alexander
    OIL & GAS JOURNAL, 2007, 105 (23) : 66 - +
  • [6] Effect of subsea dispersant application on deepwater oil spill in the South China Sea
    Chen, Haibo
    JOURNAL OF OCEANOLOGY AND LIMNOLOGY, 2022, 40 (03) : 950 - 968
  • [7] Effect of subsea dispersant application on deepwater oil spill in the South China Sea
    Haibo CHEN
    JournalofOceanologyandLimnology, 2022, 40 (03) : 950 - 968
  • [8] Effect of subsea dispersant application on deepwater oil spill in the South China Sea
    Haibo Chen
    Journal of Oceanology and Limnology, 2022, 40 : 950 - 968
  • [9] Harald valve station - A Danish subsea installation in the North Sea
    Fog, NG
    Jonsson, PH
    PROCEEDINGS OF THE SEVENTH (1997) INTERNATIONAL OFFSHORE AND POLAR ENGINEERING CONFERENCE, VOL I, 1997, 1997, : 387 - 393
  • [10] The simulation model of hummocks impact on the sea bottom and subsea pipelines
    Bekker, AT
    Sabodash, OA
    Vavilin, RV
    PROCEEDINGS OF THE SIXTH (2004 ) ISOPE PACIFIC/ASIA OFFSHORE MECHANICS SYMPOSIUM, 2004, : 111 - 116