The empirical relationship between contractor success and project innovation

被引:2
|
作者
Langston, Craig [1 ]
机构
[1] Bond Univ, Fac Soc & Design, Gold Coast, Australia
关键词
Project innovation; Head contractor success; Project delivery success; Value for money; INDUSTRY; 4.0; CONSTRUCTION PROJECTS; PRODUCTIVITY; AUTOMATION; ACCIDENTS; DECISION; QUALITY;
D O I
10.1108/ECAM-05-2021-0460
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose Innovation during project delivery is contested space. The aim in this research is to empirically explore the theory of this contested space and how project implementation can be optimized by the contractor to deliver better outcomes. It is hypothesized that project innovation has a proportional and measurable relationship to contractor success. Design/methodology/approach Based on a novel conceptual framework, this research applies a case study methodology to analyse 31 construction projects undertaken by a single Australian middle-tier contractor. Benefits from innovation are not often equitably shared. There are risks and rewards. The project innovation zone is defined as a combination of three key performance indicators - efficacy, efficiency and margin - merged into a single index that most likely shows evidence of "working smarter". Findings Client-contractor project innovation (c2pi) is demonstrated to be strongly correlated with head contractor success (HCS), yielding an r(2) value of 71%. Innovative projects mostly show positive change in efficacy, efficiency and margin when comparing "planned" and "actual" outcomes. Across the cases studied, 35% demonstrated likely evidence of innovative delivery and 52% demonstrated evidence of success from the construction contractor's perspective. Originality/value These findings verify that, within the studied sample, the pursuit of innovation leads to projects that are likely to also have greater success for the head contractor, evidenced by the mix of five critical success factors: finishing on schedule, making profit, and having less defects, less accidents and higher quality workmanship. These outcomes arguably also apply to sub-contractors, where the head contractor assumes the role of "client".
引用
收藏
页码:2231 / 2254
页数:24
相关论文
共 50 条
  • [1] An empirical investigation of the relationship between intellectual capital and project success
    Handzic, Meliha
    Durmic, Nermina
    Kraljic, Adnan
    Kraljic, Tarik
    [J]. JOURNAL OF INTELLECTUAL CAPITAL, 2016, 17 (03) : 471 - 483
  • [2] Relationship between contractor satisfaction and project management performance
    Skitmore, Martin
    Xiong, Bo
    Xia, Bo
    Masrom, Asrul
    Newton, Sidney
    [J]. CONSTRUCTION ECONOMICS AND BUILDING, 2020, 20 (04): : 1 - 24
  • [3] The Relationship between IT Adoption, IS Success and Project Success
    Nguyen, Thanh D.
    Nguyen, Tuan M.
    Cao, Thi H.
    [J]. 2016 INTERNATIONAL CONFERENCE ON ADVANCES IN COMPUTING, COMMUNICATIONS AND INFORMATICS (ICACCI), 2016, : 1192 - 1198
  • [4] An empirical analysis of the relationship between cost of control activities and project management success
    Al-Tmeemy, Samiaah
    Al Bassam, Bassam
    [J]. 3RD INTERNATIONAL CONFERENCE ON BUILDINGS, CONSTRUCTION AND ENVIRONMENTAL ENGINEERING, BCEE3-2017, 2018, 162
  • [5] The Relationship Between Project Success and Project Efficiency
    Serrador, Pedro
    Turner, Rodney
    [J]. PROJECT MANAGEMENT JOURNAL, 2015, 46 (01) : 30 - 39
  • [6] The relationship between project governance and project success
    Joslin, Robert
    Muller, Ralf
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (04) : 613 - 626
  • [7] The Relationship between Project Success and Project Efficiency
    Serrador, Pedro
    Turner, J. Rodney
    [J]. SELECTED PAPERS FROM THE 27TH IPMA (INTERNATIONAL PROJECT MANAGEMENT ASSOCIATION), 2014, 119 : 75 - 84
  • [8] Research on the Relationship between Contractor's Project Competence and Performance
    Xu, Dongming
    [J]. PROCEEDINGS OF 2010 INTERNATIONAL CONFERENCE ON CONSTRUCTION AND REAL ESTATE MANAGEMENT, VOLS 1-3, 2010, : 846 - 849
  • [9] The empirical relationship between success factors and dimensions The perspectives of World Bank project supervisors and managers
    Ika, Lavagnon A.
    Diallo, Amadou
    Thuillier, Denis
    [J]. INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2011, 4 (04) : 711 - 719
  • [10] THE RELATIONSHIP BETWEEN PROJECT TEAM DYNAMIC FEATURE, CONFLICT DIMENSION AND PROJECT SUCCESS - AN EMPIRICAL RESEARCH FROM SHANGHAI, CHINA
    Wu Guang-dong
    [J]. PAKISTAN JOURNAL OF STATISTICS, 2013, 29 (06): : 935 - 952