A case study on design and construction of mined tunnel in challenging ground conditions in Singapore

被引:0
|
作者
Jinrong, Y. [1 ]
Claudia, M. [1 ]
Sharique, K. [2 ]
Venkatesh, G. [3 ]
机构
[1] COWI Singapore Pte Ltd, Singapore, Singapore
[2] COWI India Ltd, Gurugram, India
[3] Leighton Contractors Asia Ltd, Singapore Branch, Singapore, Singapore
关键词
D O I
10.1201/9781003348030-238
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper presents a case study on design and construction of mined tunnel for DTSS2 in Singapore. The geological condition comprises excavation in soft soil, hard rock as well as unexpected fault zone with high water permeability. The analysis methods for mined tunnel in rock used included the Q-system, analytical closed-form calculations, kinematic analysis using the Unwedge software, while the analysis method for mined tunnel in soil was carried out using finite element method with ground stress relaxation assessment. Mechanical excavation with hydraulic breakers and excavators were adopted for construction of the mined tunnel. Probe drilling and grouting were carried out to form a water-tight zone surrounding the tunnel profile. Convergence points were installed and monitored to ensure the movement of the mined tunnel is within design limit. The excavation of the mined tunnel has completed in March 2022, the maximum convergence of mined tunnel recorded was well within the design work suspension level.
引用
收藏
页码:1979 / 1987
页数:9
相关论文
共 50 条
  • [11] Construction of INA to Jorbagh upline tunnel - Tunnelling in unfavourable conditions - A case study
    Malik, Sanjeev
    Agrawal, Paras Kumar
    Billore, Umesh
    Indian Concrete Journal, 2010, 84 (02): : 59 - 64
  • [12] Tunnel volume loss study on various geological conditions in Singapore
    Ma, C. B.
    Su, Thiri
    Kumarasamy, J.
    Goh, K. H.
    PROCEEDINGS OF THE ITA-AITES WORLD TUNNEL CONGRESS 2023, WTC 2023: Expanding Underground-Knowledge and Passion to Make a Positive Impact on the World, 2023, : 2062 - 2069
  • [13] Design and analysis of squeezing ground hydropower tunnel in the Himalaya through a case study
    Karki, S.
    Karki, B.
    Chhushyabaga, B.
    Khadka, S.S.
    Lowland Technology International, 2020, 21 (04) : 268 - 278
  • [14] Assessment for shallow and large tunnel construction in weak ground conditions: Application of tunnel boring machines
    Servet Karahan
    Candan Gokceoglu
    Deep Underground Science and Engineering, 2025, 4 (01) : 132 - 148
  • [15] Assessment for shallow and large tunnel construction in weak ground conditions: Application of tunnel boring machines
    Karahan, Servet
    Gokceoglu, Candan
    DEEP UNDERGROUND SCIENCE AND ENGINEERING, 2025, 4 (01) : 132 - 148
  • [16] Design and Performance Evaluation of Temporary Working Platforms in Challenging Ground Conditions
    Pouya, Kaveh Ranjbar
    Oskooei, Parisa Rahimzadeh
    Lau, Jeffrey
    Menton, Paul
    PROCEEDINGS OF THE 5TH INTERNATIONAL CONFERENCE ON TRANSPORTATION GEOTECHNICS, VOL 4, ICTG 2024, 2025, 405 : 235 - 243
  • [17] Evaluation of Surface Ground Vibrations Induced by Tunnel Blasts During Railway Construction: A Case Study
    Lee, Joon Kyu
    Jung, Young Ho
    TRANSPORTATION INFRASTRUCTURE GEOTECHNOLOGY, 2024, 11 (05) : 2885 - 2902
  • [18] Construction practice of water conveyance tunnel among complex geotechnical conditions: a case study
    Kaimin Duan
    Guofeng Zhang
    Hui Sun
    Scientific Reports, 13
  • [19] Construction practice of water conveyance tunnel among complex geotechnical conditions: a case study
    Duan, Kaimin
    Zhang, Guofeng
    Sun, Hui
    SCIENTIFIC REPORTS, 2023, 13 (01)
  • [20] Contractor prequalification and bid evaluation for design and construction of the Deep Tunnel Sewer System in Singapore
    O'Carroll, J.
    Van Weele, B.
    Kohler, C.
    NORTH AMERICAN TUNNELING 2006, 2006, : 107 - +