Research on an Assembly Building Buffer Zone Based on Gray Critical Chain

被引:0
|
作者
Chen, Jiaying [1 ]
Ye, Ziyang [1 ]
Ye, Zehui [1 ]
Sun, Qiao [1 ]
机构
[1] Dalian Univ, Sch Architectural Engn, Dalian 116622, Peoples R China
来源
APPLIED SCIENCES-BASEL | 2023年 / 13卷 / 24期
关键词
assembled building; OPA; entropy weight method; grey critical chain; buffer size; optimize construction period; MANAGEMENT; DECISION; PROJECT;
D O I
10.3390/app132413174
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
The complexity of construction in prefabricated buildings makes it vulnerable to uncertainty in project timelines, and traditional project timeline management is insufficient to control project timelines for prefabricated buildings. Therefore, research on project timeline management for prefabricated buildings is needed in order to optimize project timelines and improve project execution rates. This study proposed an improved method of setting prefabricated building buffer zones through the use of improved grey critical chain technology. Five major factors affecting project timelines in actual prefabricated construction projects were selected: personnel experience, degree of prefabrication, technical complexity, reasonableness of construction plans, and degree of construction space availability. The OPA technique was introduced and combined with the entropy weight method to improve the comprehensive weight coefficient of the grey critical chain calculation of the factors affecting the timeline. Other influencing coefficients were determined, and a new calculation method for the size of prefabricated building buffer zones was proposed. Monte Carlo simulations were conducted in Matlab on actual construction projects to ensure the scientific rationality of the improved method. The results showed that compared with the classical buffer calculation methods (cut-and-paste method, C&PM and square root standard deviation method, RSEM), the project timeline was reduced by 14.3% and 11.7%, respectively, using the improved method. The improved method not only reduces project uncertainties, but also achieves the goal of optimizing project timelines, and it is reasonable and effective. The results of the study provide a direction for the project timeline management of prefabricated building critical chains, and this method can be applied to the planning and management of prefabricated building buffer zones.
引用
下载
收藏
页数:15
相关论文
共 50 条
  • [21] Dynamic monitoring and control of a critical chain project based on phase buffer allocation
    Zhang, Junguang
    Jia, Saike
    Diaz, Estrella
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2018, 69 (12) : 1966 - 1977
  • [22] Buffer Monitoring of Critical Chain Projects Based on Support Vector Machine Prediction
    Junguang Zhang
    Qing Han
    KSCE Journal of Civil Engineering, 2023, 27 : 2745 - 2755
  • [23] The Gray Zone Between Quality Improvement and Research
    Angelos, Peter
    O'Connor, Michael F. F.
    ASAIO JOURNAL, 2023, 69 (01) : E49 - E49
  • [24] THE RESEARCH METHODS OF CRITICAL CHAIN BASED ON THE EARNED VALUE
    Wang, Liwen
    Liu, Kai
    ICIM 2010: PROCEEDINGS OF THE TENTH INTERNATIONAL CONFERENCE ON INDUSTRIAL MANAGEMENT, 2010, : 222 - 224
  • [25] Research on Software Project Schedule Based on Critical Chain
    Xu Huihua
    Wan Li
    Xue Song
    2019 5TH INTERNATIONAL CONFERENCE ON ENERGY MATERIALS AND ENVIRONMENT ENGINEERING, 2019, 295
  • [26] A Risk-Oriented Buffer Allocation Model Based on Critical Chain Project Management
    Ghoddousi, Parviz
    Ansari, Ramin
    Makui, Ahmad
    KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (05) : 1536 - 1548
  • [27] Applying critical chain in project scheduling and estimating buffer size based on fuzzy technique
    Li, Kun
    Chen, Yun-xiang
    2007 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT, VOLS 1-4, 2007, : 1068 - 1072
  • [28] A risk-oriented buffer allocation model based on critical chain project management
    Parviz Ghoddousi
    Ramin Ansari
    Ahmad Makui
    KSCE Journal of Civil Engineering, 2017, 21 : 1536 - 1548
  • [29] Buffer determination of critical chain project in segmental girders production based on comprehensive utility
    Yuan, Jianbo
    Meng, Yufen
    Zeng, Jiali
    Zhu, Xiuzhi
    Journal of Railway Science and Engineering, 2024, 21 (11) : 4779 - 4788
  • [30] Buffer sizing for the critical chain project management method
    Geekie, A.
    Steyn, H.
    SOUTH AFRICAN JOURNAL OF INDUSTRIAL ENGINEERING, 2008, 19 (01): : 73 - 88