A Dynamic Model for Effective and Optimal Planning of Formwork in Construction Projects

被引:2
|
作者
Baskova, Renata [1 ]
Tazikova, Alena [1 ]
Strukova, Zuzana [1 ]
Kozlovska, Maria [1 ]
Cabala, Jozef [1 ]
机构
[1] Tech Univ Kosice, Inst Technol Econ & Management Construct, Fac Civil Engn, Kosice 04200, Slovakia
关键词
formwork; concrete structure; modeling; cost of formwork; construction time;
D O I
10.3390/buildings13071794
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The cost of producing one cubic meter of concrete structure, depending on the structure's shape, type, and complexity, can be variously high. The cost of concrete, reinforcement, formwork, and labor ratio varies. But unlike the cost of concrete and reinforcement, which tend to be similar in the terms of the conditions of a particular construction project, the cost of formwork and work with it are different for different contractors. It often depends on the appropriateness of the formwork system used, the optimal placement of the formwork sets, the minimization of downtime, and the efficiency of the carpenters' work. Formwork modeling in the construction preparation phase intervenes in this planning area, where construction sources are defined and quantified, and the time course of their deployment is determined. The current paper deals with optimizing formwork selection and deployment in concrete structure execution. Even if several requirements must be considered when selecting and modeling the formwork (e.g., construction time, quality of concrete structure, etc.), an effort to minimize the cost of formwork, and thus construction cost, plays the most significant role. A dynamic model for effective and optimal planning of formwork in construction projects, including formwork cost analysis, is presented in the paper. The included case study demonstrated the planning of the formwork through a software application developed based on the computational algorithm of the dynamic model presented. A case study is presented in the article as a research method. An office building with five above-ground floors and one underground floor was chosen for the case study. To solve the case study, the formwork for horizontal structures (i.e., beams and slabs) is considered. The goal of the case study is to identify research questions and apply time and cost optimization to a selected specific building.
引用
收藏
页数:20
相关论文
共 50 条
  • [1] Dynamic facilities planning model for large scale construction projects
    Al Hawarneh, Alaa
    Bendak, Salaheddine
    Ghanim, Firas
    AUTOMATION IN CONSTRUCTION, 2019, 98 : 72 - 89
  • [2] Optimal planning and scheduling for repetitive construction projects
    Hyari, K
    El-Rayes, K
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2006, 22 (01) : 11 - 19
  • [3] Dynamic Planning of Construction Site for Linear Projects
    Petroutsatou, Kleopatra
    Apostolidis, Nikolaos
    Zarkada, Athanasia
    Ntokou, Aneta
    INFRASTRUCTURES, 2021, 6 (02) : 1 - 22
  • [4] An Effective Disaster Recovery Model for Construction Projects
    Anthopoulos, Leonidas G.
    Kostavara, Efrosini
    Pantouvakis, John-Paris
    SELECTED PAPERS FROM THE 26TH IPMA (INTERNATIONAL PROJECT MANAGEMENT ASSOCIATION), WORLD CONGRESS, 2013, 74 : 21 - 30
  • [5] Advanced formwork method integrated with a layout planning model for tall building construction
    Kim, Taehoon
    Lim, Hyunsu
    Lee, Ung-Kyun
    Cha, Minsoo
    Cho, Hunhee
    Kang, Kyung-In
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2012, 39 (11) : 1173 - 1183
  • [6] Towards optimal formwork pairing on construction sites
    Benoist, Thierry
    RAIRO-OPERATIONS RESEARCH, 2007, 41 (04) : 381 - 398
  • [7] Dynamic planning for fast-tracking building construction projects
    Pena-Mora, F
    Park, M
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (06): : 445 - 456
  • [8] Multiobjective Optimization Model for Planning Repetitive Construction Projects
    Altuwaim, Ayman
    El-Rayes, Khaled
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (07)
  • [9] Simulation-based Planning Model for Table Formwork Operation in Tall Building Construction
    Lim, Hyunsu
    Kim, Taehoon
    Cho, Hunhee
    Kang, Kyung-In
    JOURNAL OF ASIAN ARCHITECTURE AND BUILDING ENGINEERING, 2017, 16 (01) : 115 - 122
  • [10] Proposal of a model for the quantification of construction waste costs in the planning stage of construction projects
    Garces, Gonzalo
    Molina, Antonio
    INFORMES DE LA CONSTRUCCION, 2023, 75 (751)