Spatio-temporal optimization of construction elevator planning in high-rise building projects

被引:1
|
作者
Wu, Keyi [1 ]
de Soto, Borja Garcia [1 ]
机构
[1] New York Univ Abu Dhabi, Div Engn, SMART Construct Res Grp, Abu Dhabi, U Arab Emirates
来源
关键词
Construction hoist; Temporary elevator; Vertical transportation; Mixed-integer programming; TRANSPORTATION; SIMULATION; HOIST; TIME;
D O I
10.1016/j.dibe.2024.100328
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Appropriate construction elevator planning is beneficial for successfully completing high-rise building projects. Construction elevator planning typically remains unchanged throughout a high-rise building project or seldom involves the designation of service days, which causes such planning not to respond effectively to variable transportation demands and adversely affects the possibility of further optimization. Another limitation is that the installation and dismantlement dates of construction elevators, which are highly important when multiple construction elevators are used, cannot be explicitly determined in construction elevator planning. To solve these weaknesses, this paper proposes an approach to assign construction elevator cabs to serve designated days and floors based on actual transportation demands from the perspective of spatio-temporal optimization with mixedinteger programming. The experimental case study results show that the presented planning can significantly reduce the total cost when compared to other planning and can provide evidence and explanation for determining the installation and dismantlement dates of construction elevators.
引用
收藏
页数:25
相关论文
共 50 条
  • [1] Spatio-temporal planning for tower cranes in construction projects with simulated annealing
    Wu, Keyi
    de Soto, Borja Garcia
    Zhang, Feilian
    [J]. AUTOMATION IN CONSTRUCTION, 2020, 111
  • [2] Optimization of Vertical Elevator Movements and Material Storage Locations for High-Rise Building Construction with Overtime Cost Effects
    Huang, Chun
    Wong, C. K.
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2019, 33 (01)
  • [3] Optimization of shoring/reshoring levels in high-rise building construction
    Sohoni, Prachi
    Ghaffar, Abdul
    Matsagar, Vasant A.
    Jha, K. N.
    [J]. ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2018, 10 (01): : 1803 - 1826
  • [4] Sources of Uncertainties in Offsite Logistics of Modular Construction for High-Rise Building Projects
    Yang, Yi
    Pan, Mi
    Pan, Wei
    Zhang, Zhiqian
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2021, 37 (03)
  • [5] Multimethod Supply Chain Simulation Model for High-Rise Building Construction Projects
    Jung, Minhyuk
    Park, Moonseo
    Lee, Hyun-Soo
    Chi, Seokho
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2018, 32 (03)
  • [6] Group Elevator Scheduling during High-rise Building Evacuation
    Ding Ning
    Chen Tao
    Luh, Peter B.
    Zhang Hui
    [J]. PROCEEDINGS OF ISCRAM ASIA 2012 CONFERENCE ON INFORMATION SYSTEMS FOR CRISIS RESPONSE AND MANAGEMENT, 2012, : 229 - 235
  • [7] Multi-User Virtual Reality for Remote Collaboration in Construction Projects: A Case Study with High-Rise Elevator Machine Room Planning
    Phong Truong
    Holtta-Otto, Katja
    Becerril, Paulina
    Turtiainen, Reetta
    Siltanen, Sanni
    [J]. ELECTRONICS, 2021, 10 (22)
  • [8] Optimization of flexible lift processes on high-rise building construction sites
    Yazdi, Alireza Jalali
    Forsythe, Perry
    Fini, Alireza Ahmadian Fard
    Maghrebi, Mojtaba
    [J]. AUTOMATION IN CONSTRUCTION, 2019, 107
  • [9] Spatial Optimization in Spatio-temporal Motion Planning
    Zhang, Weize
    Yadmellat, Peyman
    Gao, Zhiwei
    [J]. 2022 IEEE INTELLIGENT VEHICLES SYMPOSIUM (IV), 2022, : 1248 - 1254
  • [10] Method to Implement Delayed Product Differentiation in Construction of High-Rise Apartment Building Projects
    da Rocha, Cecilia Gravina
    Kemmer, Sergio Luiz
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (10)