A reinforcement learning-based approach for solving multi-agent job shop scheduling problem

被引:1
|
作者
Dong, Zhuoran [1 ]
Ren, Tao [1 ]
Qi, Fang [1 ]
Weng, Jiacheng [1 ]
Bai, Danyu [2 ]
Yang, Jie [2 ]
Wu, Chin-Chia [3 ]
机构
[1] Northeastern Univ, Software Coll, Shenyang 110819, Peoples R China
[2] Dalian Maritime Univ, Sch Maritime Econ & Management, Dalian 116026, Peoples R China
[3] Feng Chia Univ, Dept Stat, Taichung, Taiwan
基金
中国国家自然科学基金;
关键词
Multi-agent; job shop scheduling; release dates; deep reinforcement learning; artificial bee colony algorithm; transformer; BEE COLONY ALGORITHM; GENETIC ALGORITHM; DISPATCHING RULES; OPTIMIZATION; BENCHMARKS; MACHINE;
D O I
10.1080/00207543.2024.2423807
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Wafer processing is the most expensive, time-consuming, and complex stage in semiconductor manufacturing. It varies significantly based on orders of customers (agents). Optimising the wafer processing flow in a multi-agent scenario can meet customised requirements, speed up delivery, and reduce costs. This work models wafer processing as a multi-agent job shop scheduling problem (MAJSP) with release dates. The objective is to minimise the total weighted makespan of agents. To address both dynamic and static scheduling scenarios in the MAJSP context, two deep reinforcement learning-based (DRL) methods are proposed. In a dynamic scheduling scenario, the statuses of orders and production resources can change at any moment. A DRL method called Graph Transformer Network (GTN) is proposed to rapidly generate high-quality solutions. In a static scheduling scenario, the production plan can be formulated based on predetermined demand and resource conditions. A novel hybrid method (GTN-DABC) that combines GTN with the discrete artificial bee colony algorithm (DABC) is proposed to provide high-quality production plans for manufacturers within an acceptable computation time. Experimental results demonstrate that the proposed GTN outperforms existing heuristics, and the well-designed GTN-DABC is more competitive than other meta-heuristics.
引用
收藏
页数:26
相关论文
共 50 条
  • [41] Research of job-shop scheduling model based on multi-agent
    College of Mechanical Engineering, Shenyang Ligong University, Shenyang 110168, China
    不详
    不详
    Dongbei Daxue Xuebao, 2008, SUPPL. (75-78):
  • [42] Deep reinforcement learning for solving the joint scheduling problem of machines and AGVs in job shop
    Sun A.-H.
    Lei Q.
    Song Y.-C.
    Yang Y.-F.
    Lei, Qi (leiqi@cqu.edu.cn), 1600, Northeast University (39): : 253 - 262
  • [43] MODEL DESIGN OF JOB SHOP SCHEDULING BASED ON MULTI-AGENT SYSTEM
    Li Qing-song
    Du Li-ming
    2009 IITA INTERNATIONAL CONFERENCE ON SERVICES SCIENCE, MANAGEMENT AND ENGINEERING, PROCEEDINGS, 2009, : 233 - 236
  • [44] Improved job-shop scheduling method based on multi-agent
    Xu, Xinli
    Wang, Xiangli
    Wang, Wanliang
    WSEAS Transactions on Information Science and Applications, 2006, 3 (07): : 1308 - 1315
  • [45] A centralized reinforcement learning method for multi-agent job scheduling in Grid
    Moradi, Milad
    2016 6TH INTERNATIONAL CONFERENCE ON COMPUTER AND KNOWLEDGE ENGINEERING (ICCKE), 2016, : 171 - 176
  • [46] Deteriorating job scheduling problem in a job-shop manufacturing system by multi-agent system
    Renna, Paolo
    INTERNATIONAL JOURNAL OF COMPUTER INTEGRATED MANUFACTURING, 2015, 28 (09) : 936 - 945
  • [47] Multi-Agent Reinforcement Learning-Based Fairness-Aware Scheduling for Bursty Traffic
    Yuan, Mingqi
    Cao, Qi
    Pun, Man-On
    Chen, Yi
    2021 IEEE GLOBAL COMMUNICATIONS CONFERENCE (GLOBECOM), 2021,
  • [48] Learning-based multi-agent MPC for irrigation scheduling
    Agyeman, Bernard T.
    Naouri, Mohamed
    Appels, Willemijn M.
    Liu, Jinfeng
    Shah, Sirish L.
    CONTROL ENGINEERING PRACTICE, 2024, 147
  • [49] Multi-Agent System for Flexible Job-shop Scheduling Problem Based on Human Immune System
    Xiong Wei
    Fu Dongmei
    PROCEEDINGS OF THE 31ST CHINESE CONTROL CONFERENCE, 2012, : 2476 - 2480
  • [50] Ant Colony Optimization for the Job Shop Scheduling Problem using Multi-Agent Systems
    Xiang, W
    Fox, B
    Lee, HP
    ICAI '05: PROCEEDINGS OF THE 2005 INTERNATIONAL CONFERENCE ON ARTIFICIAL INTELLIGENCE, VOLS 1 AND 2, 2005, : 898 - 904