Predicting construction delay risks in Saudi Arabian projects: A comparative analysis of CatBoost, XGBoost, and LGBM

被引:0
|
作者
Alsulamy, Saleh [1 ]
机构
[1] King Khalid Univ, Architecture & Planning Coll, Dept Architecture, Abha 61421, Saudi Arabia
关键词
Construction delay; Predictive analytics; Machine learning algorithms; CatBoost; XGBoost; LGBM; MODEL;
D O I
10.1016/j.eswa.2024.126268
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Accurately forecasting construction delay risks is essential for effective project management in the construction industry. This study evaluates the performance of three machine learning algorithms CatBoost, XGBoost, and LGBM in predicting construction delays for Saudi Arabian projects with varying levels of Time Overrun (TO). Model efficiency is assessed using key performance metrics, including accuracy, misclassification error, precision, sensitivity, specificity, false positive rate (FPR), and false negative rate (FNR). The results demonstrate that LGBM outperforms CatBoost and XGBoost across all TO categories. For projects with less than 30% TO, LGBM achieves the highest accuracy and sensitivity. In the 30%-60% TO category, it continues to excel, particularly in accuracy and sensitivity. For projects exceeding 60% TO, LGBM maintains its lead with superior accuracy, sensitivity, and specificity. These findings establish LGBM as a highly effective algorithm for predicting construction delays, offering valuable insights for risk assessment and management in the construction sector. While CatBoost and XGBoost also deliver strong performance, showcasing their ability to predict delays across various TO levels, LGBM's consistent superiority highlights its robustness and reliability. This study advances the application of predictive analytics in construction delay risk management, paving the way for the development of effective risk mitigation strategies.
引用
收藏
页数:14
相关论文
共 50 条
  • [31] Delay causes analysis in complex construction projects: a Semantic Network Analysis approach
    Zarei, Behrouz
    Sharifi, Hossein
    Chaghouee, Yahya
    PRODUCTION PLANNING & CONTROL, 2018, 29 (01) : 29 - 40
  • [32] Forecasting delay-time model for Saudi construction projects using DEMATEL-SD technique
    Al-Gahtani, Khalid
    Alsugair, Abdulah
    Alsanabani, Naif
    Alabduljabbar, Abdulmajeed
    Almutairi, Bader
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (11) : 1225 - 1239
  • [33] Analysis and prioritisation of critical delay factors in construction projects: A Colombian case
    Ovalle, Oscar Rubiano
    Correa-Cepeda, Daniela
    Estrada-Cifuentes, Juan P.
    Mopan, Yesid Anacona
    ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2024, 16 (01): : 237 - 250
  • [34] Critical path effect based delay analysis method for construction projects
    Yang, Jyh-Bin
    Kao, Chih-Kuei
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2012, 30 (03) : 385 - 397
  • [35] Factors influencing the selection of delay analysis methods in construction projects in UAE
    Abdelhadi, Yazeed
    Dulaimi, Mohammed Fadhil
    Bajracharya, Arun
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, 19 (04) : 329 - 340
  • [36] Longevity of risks in software development projects: a comparative analysis with an academic environment
    Alves, Luis M.
    Souza, Gustavo
    Ribeiro, Pedro
    Machado, Ricardo J.
    INTERNATIONAL CONFERENCE ON ENTERPRISE INFORMATION SYSTEMS / INTERNATIONAL CONFERENCE ON PROJECT MANAGEMENT / INTERNATIONAL CONFERENCE ON HEALTH AND SOCIAL CARE INFORMATION SYSTEMS AND TECHNOLOGIES 2020 (CENTERIS/PROJMAN/HCIST 2020), 2021, 181 : 827 - 834
  • [37] Discriminant analysis for predicting ranges of cost variance in international construction projects
    Kim, Du Y.
    Han, Seung H.
    Kim, Hyoungkwan
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2008, 134 (06) : 398 - 410
  • [38] Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects
    Sanchez, Omar
    Castaneda, Karen
    Mejia, Guillermo
    Pellicer, Eugenio
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 223 - 231
  • [39] Quantitative Risk Analysis for Construction Projects Considering Risks Correlations and Fuzzy Logic
    Cuadros-Lopez, Alvaro Julio
    Arevalo, Nicolle Alexandra Cruces
    Ortiz, Claudia
    UIS INGENIERIAS, 2024, 23 (01):
  • [40] An Exploratory Analysis of Risks in Green Residential Building Construction Projects: The Case of Singapore
    Hwang, Bon-Gang
    Shan, Ming
    Phua, Helena
    Chi, Seokho
    SUSTAINABILITY, 2017, 9 (07)