COMMISSIONING OF NO. 5 BLAST FURNACE AT PORT KEMBLA.

被引:0
|
作者
Devine, J.T.
Warner, R.E.
机构
关键词
D O I
暂无
中图分类号
学科分类号
摘要
Present capacity for molten iron production at Port Kembla is an average of 13 000 t/day from five blast furnaces. The most recently installed blast furnace, No. 5, was commissioned in March 1972 with a design capacity of 4 500 t/day. For the first reline currently scheduled for 1977, plans are being finalized for significant modifications and uprating of capacity. Achievement of the initial design capacity from No. 5 blast furnace on a sustained bases was not realized until the third year of operation. Although the furniture is only 42% larger than No. 4 blast furnace on an inner volume basis, the more stringent raw materials, operation and maintenance requirements of the larger furnace and more complex equipment have been found to be much more critical than anticipated in the planning stages. The problem areas include the failure of the shower cooled bosh, failure of the upper shaft brickwork, sludge deposition in cigar coolers, dustcatcher blockages, tuyere stock limitations to blast temperature, taphole clay and machinery inadequacies, hot metal ladle availability and coke quality.
引用
收藏
相关论文
共 50 条
  • [31] Actions and control of CST blast furnace No. 2 hearth
    Novaes, J.-A. Pereira
    da Cruz, R., Jr.
    da Silva, M. Correa
    Gushiken, J. Issamu
    Barros, R.-J. Tauffer
    de Oliveira, M. Azevedo
    [J]. REVUE DE METALLURGIE-CAHIERS D INFORMATIONS TECHNIQUES, 2005, 102 (03): : 183 - 188
  • [32] Burden distribution studies for Gary No. 4 blast furnace
    Yaniga, SE
    Howell, JL
    Gray, J
    [J]. 60TH IRONMAKING CONFERENCE PROCEEDINGS, 2001, 60 : 57 - 69
  • [33] Long campaign life of CST No. 1 blast furnace
    Klein, CA
    Rezende, RG
    Fujihara, FK
    Gushiken, JI
    [J]. STAHL UND EISEN, 2005, 125 (06): : S13 - +
  • [34] Interim repair of the Lake Erie works' No. blast furnace
    McChesney, S.C.
    Braun, C.H.
    [J]. Iron and Steel Engineer, 1990, 67 (06):
  • [35] Relining and enlargement of Rogesa No. 4 blast furnace in 2003
    Hartig, W.
    Reufer, F.
    Beermann, R.
    [J]. REVUE DE METALLURGIE-CAHIERS D INFORMATIONS TECHNIQUES, 2005, 102 (7-8): : 517 - 524
  • [37] COMPUTER CONTROL OF INLANDS NO 5 BLAST FURNACE
    ROBINS, NA
    [J]. BLAST FURNACE AND STEEL PLANT, 1967, 55 (12): : 1090 - &
  • [38] No 5 Blast Furnace 1995 reline & upgrade
    Kakascik, TF
    [J]. 55TH IRONMAKING CONFERENCE PROCEEDINGS, 1996, 55 : 181 - 182
  • [39] PROCESS CONTROL SYSTEM OF KOKURA No. 2 BLAST FURNACE.
    Matoba, Yoshiyuki
    Otsuka, Koichi
    Mochizuki, Ken
    Ueno, Yasunaga
    [J]. Kang T'ieh/Iron and Steel (Peking), 1985, 20 (11): : 64 - 68
  • [40] Short term revamping of No. 6 blast furnace in Chiba Works
    Fujita, M
    Kojima, H
    Marushima, H
    Matumoto, T
    Yokogawa, A
    [J]. REVUE DE METALLURGIE-CAHIERS D INFORMATIONS TECHNIQUES, 1999, 96 (03): : 349 - 357