LEARNINGS FROM IMPLEMENTING AN API 1173 COMPLIANT MANAGEMENT SYSTEM

被引:0
|
作者
Potter, Dale [1 ]
Jean, Mark S. [2 ]
机构
[1] CHS, Mcpherson, KS 67460 USA
[2] Applied4Sight Ltd, Calgary, AB, Canada
关键词
pipeline safety management system; PSMS; API RP 1173; governance; safety culture; risk management; management review; performance; management system; operational excellence; maturity assessment;
D O I
暂无
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
In July of 2015, the American Petroleum Institute (API) published Recommended Practice (RP) 1173 to provide an industry framework for the development of a Pipeline Safety Management System (PSMS). Regulators and industry companies worked together to develop the RP, providing the basis for enhanced public safety and protection. Recognizing the inherent benefits to their organization, CHS' pipelines and terminals division began developing their API RP 1173 compliant management system in February 2016. They were early adopters of this new management system approach and have had several years to not only develop their frameworks, policies, procedures, templates, and tools, but also to implement and ingrain them within their organization. The approach taken was methodic and systematic and focussed on right-sizing their system to match their specific organizational requirements. This supported CHS' focus on building and applying the right pieces of their system in the right order to build organizational momentum and adoption. Roles and responsibilities throughout the organization were carefully defined to support implementation, administration, and management of the system. The establishment of CHS' management system not only supported improved safety, but it also helped support the integration and alignment of different pipeline business areas. Throughout CHS' development and implementation of its management system, key challenges and learnings were identified. This paper will outline the approach taken by CHS to assess and implement API RP 1173 within their pipeline and terminals division. The paper will outline the specific steps taken, the approach to building their company-specific framework and the learnings that were discovered along their journey. This paper will be of specific interest to those companies that may be in various stages of developing and implementing API RP 1173 within their respective organizations.
引用
收藏
页数:10
相关论文
共 50 条
  • [41] Implementing of quality management system - Macedonian experience
    Grubovic, R. M.
    Velkova, E.
    Veljanovski, N.
    Useini, S.
    Petkovikj, E.
    Grubovic, M.
    BONE MARROW TRANSPLANTATION, 2015, 50 : 5546 - 5547
  • [42] Selecting and Implementing an Environmental Management Information System
    Gilbert, Jill Barson
    EM: Air and Waste Management Association's Magazine for Environmental Managers, 1999, (JULY): : 13 - 20
  • [43] Learnings from a Pilot Hybrid Question Answering System: CQAS
    Shan, Alvina Lee Hui
    Shankararamen, Venky
    Lieh, Ouh Eng
    PROCEEDINGS OF THE 23RD ANNUAL INTERNATIONAL CONFERENCE ON DIGITAL GOVERNMENT RESEARCH, DGO 2022: Intelligent Technologies, Governments and Citizens, 2022, : 437 - 439
  • [44] Implementing of the purchasing management system and the enterprise Intranet
    Xu, Huahu
    Gao, Jue
    Sun, Hongguang
    Jisuanji Gongcheng/Computer Engineering, 2000, 26 (01): : 97 - 98
  • [45] Implementing ERMS: Electronic Records Management System
    Gunnlaugsdottir, Johanna
    ICELANDIC REVIEW OF POLITICS & ADMINISTRATION, 2007, 3 (02):
  • [46] IMPLEMENTING AN AUTOMATED MAINTENANCE MANAGEMENT-SYSTEM
    MARTIN, HJ
    BIRT, JC
    LEAKE, WH
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1984, 46 : 667 - 667
  • [47] IMPLEMENTING AND USING THE DATABASE-MANAGEMENT SYSTEM
    RUSSELL, JE
    COMPUTER PHYSICS COMMUNICATIONS, 1986, 41 (2-3) : 393 - 395
  • [48] Case study: Implementing a content management system
    Jones, CP
    Mitchko, J
    Overcash, M
    NAVIGATING THE FUTURE OF TECHNICAL COMMUNICATION, 2004, : 221 - 224
  • [49] IMPLEMENTING THE INTERNAL CONTROL & FINANCIAL MANAGEMENT SYSTEM
    Athenaeum, Marcel Ghita
    METALURGIA INTERNATIONAL, 2009, 14 (06): : 73 - 76
  • [50] Problems of Implementing System Analysis in the Target Management
    Zvyagin, L. S.
    2017 IEEE II INTERNATIONAL CONFERENCE ON CONTROL IN TECHNICAL SYSTEMS (CTS), 2017, : 293 - 296