Spillway radial gate failure at Folsom Dam, California

被引:0
|
作者
Todd, RV [1 ]
机构
[1] US Bur Reclamat, Denver Tech Serv Ctr, Mech Equipment Grp, Denver, CO 80225 USA
来源
DEALING WITH AGING DAMS | 1999年
关键词
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
On the morning of July 17, 1995, spillway radial gate No.3 failed at Folsom Dam, California. It was one of five service gates which had been operated by the Bureau of Reclamation since 1956. There was no warning of structural distress prior to the failure. No one was injured, even though there was a sustained release of 1,132 m(3)/s into the Lower American River. A multi-disciplinary, multi-agency forensic team was formed to investigate the failure. All of the remaining gates were thoroughly inspected for signs of structural degradation, apart from some corrosion, nothing detrimental was found. The failed gate was removed and then thoroughly examined to determine the mode of failure. This examination determined that a diagonal brace joint, adjacent to the trunnion was the initial point of failure. Theoretical finite element models substantiated this study when a trunnion friction coefficient of 0.25 was considered. This value had been confirmed also from friction tests performed on the actual trunnion from the failed gate. Trunnion friction moment was the key factor, and it had been omitted in the original design calculations.
引用
收藏
页码:15 / 29
页数:15
相关论文
共 50 条
  • [21] EXPERIENCE IN RECONSTRUCTING THE RADIAL GATE OF THE SPILLWAY AT THE VILYUI HYDROELECTRIC STATION.
    Sitnyanskii, A.I.
    Hydrotechnical Construction, 1984, 18 (09): : 414 - 418
  • [22] Computational Fluid Dynamic Analysis at Dam Spillway due to Different Gate Openings
    Zawawi, M. H.
    Aziz, N. A.
    Radzi, M. R. M.
    Hassan, N. H.
    Ramli, M. Z.
    Zahari, N. M.
    Abbas, M. A.
    Saleha, A.
    Salwa, A.
    Muda, Z. C.
    GREEN DESIGN AND MANUFACTURE: ADVANCED AND EMERGING APPLICATIONS, 2018, 2030
  • [23] Cusset dam Spillway
    Barcouda, M
    Guene, C
    HOUILLE BLANCHE-REVUE INTERNATIONALE DE L EAU, 2004, (04): : 39 - 45
  • [24] Study on Water Flow Capacity and Related Parameters of Spillway Gate of Orifice Outflow Dam
    Lu, Yaxia
    Sun, Xushu
    WATER CONSERVATION SCIENCE AND ENGINEERING, 2021, 6 (04) : 191 - 200
  • [25] Study on Water Flow Capacity and Related Parameters of Spillway Gate of Orifice Outflow Dam
    Yaxia Lu
    Xushu Sun
    Water Conservation Science and Engineering, 2021, 6 : 191 - 200
  • [26] Numerical Simulation of Hydraulic Characteristics of Spillway Tunnel in the Radial Gate Closing Process
    Ma Xudong
    Yang Qing
    Dai Guangqing
    Xu Jie
    PROCEEDINGS OF THE 35TH IAHR WORLD CONGRESS, VOLS I AND II, 2013, : 4801 - 4809
  • [27] Chaotic Characteristic Analysis of Spillway Radial Gate Vibration under Discharge Excitation
    Lu, Yangliang
    Liu, Yakun
    Zhang, Di
    Cao, Ze
    Fu, Xuemin
    APPLIED SCIENCES-BASEL, 2024, 14 (01):
  • [29] Blasting a tunnel through Folsom Dam
    Revey, GF
    Scott, GA
    PROCEEDINGS OF THE TWENTY-FIFTH ANNUAL CONFERENCE ON EXPLOSIVES AND BLASTING TECHNIQUE, VOL I, 1999, : 149 - 158
  • [30] Folsom Dam outlet works modifications
    Hall, EW