Reliability/risk centered cost effective preventive maintenance planning of generating units

被引:6
|
作者
Umamaheswari, E. [1 ]
Ganesan, S. [1 ]
Abirami, M. [1 ]
Subramanian, S. [1 ]
机构
[1] Annamalai Univ, Dept Elect Engn, Cuddalore, India
关键词
Fuzzy decision-making mechanism ant lion optimization; Loss of load expectation; Preventive maintenance scheduling; Sum of squares of reserve; Total operating cost;
D O I
10.1108/IJQRM-03-2017-0039
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Purpose Finding the optimal maintenance schedules is the primitive aim of preventive maintenance scheduling (PMS) problem dealing with the objectives of reliability, risk and cost. Most of the earlier works in the literature have focused on PMS with the objectives of leveling reserves/risk/cost independently. Nevertheless, very few publications in the current literature tackle the multi-objective PMS model with simultaneous optimization of reliability, and economic perspectives. Since, the PMS problem is highly nonlinear and complex in nature, an appropriate optimization technique is necessary to solve the problem in hand. The paper aims to discuss these issues. Design/methodology/approach The complexity of the PMS problem in power systems necessitates a simple and robust optimization tool. This paper employs the modern meta-heuristic algorithm, namely, Ant Lion Optimizer (ALO) to obtain the optimal maintenance schedules for the PMS problem. In order to extract best compromise solution in the multi-objective solution space (reliability, risk and cost), a fuzzy decision-making mechanism is incorporated with ALO (FDMALO) for solving PMS. Findings As a first attempt, the best feasible maintenance schedules are obtained for PMS problem using FDMALO in the multi-objective solution space. The statistical measures are computed for the test systems which are compared with various meta-heuristic algorithms. The applicability of the algorithm for PMS problem is validated through statistical t-test. The statistical comparison and the t-test results reveal the superiority of ALO in achieving improved solution quality. The numerical and statistical results are encouraging and indicate the viability of the proposed ALO technique. Originality/value As a maiden attempt, FDMALO is used to solve the multi-objective PMS problem. This paper fills the gap in the literature by solving the PMS problem in the multi-objective framework, with the improved quality of the statistical indices.
引用
下载
收藏
页码:2052 / 2079
页数:28
相关论文
共 50 条
  • [31] Performance-Based Reliability-Centered Maintenance Planning for Hospital Facilities
    Salah, Mohamed
    Osman, Hesham
    Hosny, Ossama
    JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES, 2018, 32 (01)
  • [32] Reliability centered maintenance: A solution to optimise mass transit system cost effectiveness
    D'Addio, GF
    Firpo, P
    Savio, S
    INTERNATIONAL CONFERENCE ON DEVELOPMENTS IN MASS TRANSIT SYSTEMS, 1998, : 211 - 216
  • [33] Risk-based maintenance for reliability and cost reduction
    Wright, GJ
    INTERNATIONAL CONFERENCE AND WORKSHOP ON RELIABILITY AND RISK MANAGEMENT, 1998, : 545 - 560
  • [34] Design for Lifecycle Cost and Preventive Maintenance Using Time-Dependent Reliability
    Singh, Amandeep
    Mourelatos, Zissimos P.
    Li, Jing
    MATERIALS AND PRODUCT TECHNOLOGIES, 2010, 118-120 : 10 - 16
  • [35] Machine Maintenance Planning with Reliability Centered Maintenance to Increase Product Quality Reliability in The Indonesian Automotive Industry Systematic Literature Review
    Sarjono, Haryadi
    Trisnianto, Muhammad Muladi
    Handoko, Bambang Leo
    ACM International Conference Proceeding Series, 2021, : 291 - 297
  • [36] Optimal Policy Study on Reliability-Centered Preventive Maintenance for a Single-Equipment System
    Liu, Q. M.
    Dong, M.
    Lv, W. Y.
    ENGINEERING ASSET MANAGEMENT - SYSTEMS, PROFESSIONAL PRACTICES AND CERTIFICATION, 2015, : 995 - 1002
  • [37] Maintenance Cost Optimization On Reliability Centered Maintenance Based On Failure Rate on Flash Gas Compression System
    Riswanto, Friandi D.
    Biyanto, Totok Ruki
    Iballe, Thareq Fasya
    Adista, Afin Osi
    Putra, Samuel Dian Permana
    Abdillah, Arfiq Isa
    ADVANCED INDUSTRIAL TECHNOLOGY IN ENGINEERING PHYSICS, 2019, 2088
  • [38] Quantified Risk Ranking Model for Condition-Based Risk and Reliability Centered Maintenance
    Chattopadhyaya P.K.
    Basu S.K.
    Majumdar M.C.
    Journal of The Institution of Engineers (India): Series C, 2017, 98 (3) : 325 - 333
  • [39] Determination of cost-effective preventive maintenance schedule for a telecommunication software system
    Dohi, T
    Kaio, N
    Osaki, S
    ELECTRONICS AND COMMUNICATIONS IN JAPAN PART III-FUNDAMENTAL ELECTRONIC SCIENCE, 2003, 86 (07): : 41 - 50
  • [40] The effect of energy purchase cost in maintenance schedule of generating units based on genetic algorithm
    Eshraghnia, Roozbeh
    Shanechi, Mohammad Hasan Modir
    Riahi, Reza
    2007 MEDITERRANEAN CONFERENCE ON CONTROL & AUTOMATION, VOLS 1-4, 2007, : 1203 - 1210