摘要
Formwork system is a significant constituent and a basic requirement for high-rise cast-in-place reinforced concrete buildings. Usually, the builders are confronted with the decision to choose the safe, optimum number of levels of shores/reshores for a predetermined safety factor and given grade of concrete, giving due consideration to the cost of formwork system. In this study, MATLAB program is developed to calculate the load distribution between the interconnected slabs and levels of shore/reshore of a slab formwork based on a simplified method. This program is further modified by incorporating genetic algorithm for the optimization of cost of construction for high-rise building. The cost of level of shores and reshores per floor is defined as a function of cycle time which directly reflects the increase in the cost of construction. Various combinations of shore and reshore levels with several grades of concrete for various safety factors are checked to minimize the cost of construction. The optimization equation is solved using genetic algorithm considering appropriate constraints to practically ensure feasible solutions. The case of one level of shores and numerous levels of reshores is better than one level of reshores and numerous levels of shores. The result of certain combination of shore and reshore levels is not the same when the level numbers are reversed. A comparative study is carried out to check the optimum cost for various safety factors. The program is useful for the designers to decide the levels of shores and reshores with minimized cost without compromising the safety of construction.
引用
收藏
页码:1803 / 1826
页数:24
相关论文
共 50 条
  • [41] Optimization of Vertical Elevator Movements and Material Storage Locations for High-Rise Building Construction with Overtime Cost Effects
    Huang, Chun
    Wong, C. K.
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2019, 33 (01)
  • [42] Study on Selection and Optimization of Vertical Transportation Equipment for High-rise Construction
    Qi, Xijing
    Zhou, Xiaohu
    Song, Mingliang
    Li, Fengming
    [J]. ADVANCES IN BUILDING MATERIALS, PTS 1-3, 2011, 168-170 : 2376 - +
  • [43] HIGH-RISE BUILDING AND METROPOLITAN LANDSCAPE
    Montenegro-Miranda, German
    [J]. BITACORA URBANO TERRITORIAL, 2018, 28 (02): : 73 - 82
  • [44] Exhaust in a high-rise residential building
    Spielman, Alexander
    [J]. TAB Journal, 2002, (SUMMER 2002):
  • [45] Transformation design of a high-rise building
    Yang, Xiaodong
    Wei, Qiang
    Li, Junfeng
    [J]. ADVANCES IN CIVIL STRUCTURES, PTS 1 AND 2, 2013, 351-352 : 1038 - 1042
  • [46] Reach for the skies (High-rise building)
    Dawson, Layla
    [J]. ARCHITECTURAL REVIEW, 2007, 221 (1319) : 88 - 88
  • [47] STAIRWELL PRESSURIZATION IN A HIGH-RISE BUILDING
    DIAS, C
    [J]. ASHRAE JOURNAL-AMERICAN SOCIETY OF HEATING REFRIGERATING AND AIR-CONDITIONING ENGINEERS, 1978, 20 (07): : 24 - 26
  • [48] Sustainable development of high-rise building
    Pan Feng
    Wu Xingkuan
    [J]. 2011 INTERNATIONAL CONFERENCE ON GREEN BUILDINGS AND SUSTAINABLE CITIES, 2011, 21 : 943 - 947
  • [49] FIRE FIGHTING IN HIGH-RISE BUILDING
    Lo, Shane Siu-hang
    [J]. PROCEEDINGS OF THE 7TH INTERNATIONAL CONFERENCE ON TALL BUILDINGS, 2010, : 353 - 364
  • [50] Progress in Study of Concrete Pumping Construction Techniques in Super High-rise Building
    Ba, Ling-Zhen
    Yang, Yi-Bo
    Liang, Song
    Mo, Hai-Hong
    Cao, Hong
    Liu, Ting-Jin
    Chen, Jun-Sheng
    [J]. ULTRA-HIGH-PUMPABILITY AND HIGH PERFORMANCE CONCRETE TECHNOLOGY, 2009, 405-406 : 110 - 116