RESOURCE INVESTMENT PROBLEM WITH DISCOUNTED CASH FLOWS

被引:0
|
作者
Najafi, Amir Abbas [1 ]
Niaki, Seyed Taghi Akhavan [1 ]
机构
[1] Sharif Univ Technol, Dept Ind Engn, POB 11365-9414,Azadi Ave, Tehran, Iran
来源
INTERNATIONAL JOURNAL OF ENGINEERING | 2005年 / 18卷 / 01期
关键词
Project Scheduling; Resource Investment; Net Present Value; Heuristic Methods;
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
A resource investment problem is a project-scheduling problem in which the availability levels of the resources are considered decision variables and the goal is to find a schedule and resource requirement levels such that some objective function optimizes. In this paper, we consider a resource investment problem in which the goal is to maximize the net present value of the project cash flows. We call this problem as Resource Investment Problem with Discounted Cash Flows (RIPDCF) and we develop a heuristic method to solve it. Results of several numerical examples show that the proposed method performs relatively well.
引用
收藏
页码:51 / 62
页数:12
相关论文
共 50 条
  • [21] Ant colony algorithm for scheduling resource constrained projects with discounted cash flows
    Shou, Yong-Yi
    PROCEEDINGS OF 2006 INTERNATIONAL CONFERENCE ON MACHINE LEARNING AND CYBERNETICS, VOLS 1-7, 2006, : 176 - +
  • [22] DISCOUNTED CASH FLOW-ANALYSIS AND UNPREDICTABLE CASH FLOWS
    TIMMONS, JD
    ARCHER, WR
    REAL ESTATE REVIEW, 1988, 18 (03): : 26 - 30
  • [23] A lagrangian relaxation and ACO hybrid for resource constrained project scheduling with discounted cash flows
    Dhananjay Thiruvady
    Mark Wallace
    Hanyu Gu
    Andreas Schutt
    Journal of Heuristics, 2014, 20 : 643 - 676
  • [24] DISCOUNTED CASH FLOW AND AGRICULTURAL INVESTMENT - REPLY
    COCKS, KD
    JOURNAL OF AGRICULTURAL ECONOMICS, 1967, 18 (02) : 294 - 294
  • [25] A lagrangian relaxation and ACO hybrid for resource constrained project scheduling with discounted cash flows
    Thiruvady, Dhananjay
    Wallace, Mark
    Gu, Hanyu
    Schutt, Andreas
    JOURNAL OF HEURISTICS, 2014, 20 (06) : 643 - 676
  • [26] FUZZY PROJECT SCHEDULING WITH DISCOUNTED CASH FLOWS
    Shavandi, Hassan
    Najafi, Amir Abbas
    Moslehirad, Alireza
    ECONOMIC COMPUTATION AND ECONOMIC CYBERNETICS STUDIES AND RESEARCH, 2012, 46 (01): : 219 - 232
  • [27] DISCOUNTED CASH FLOWS DETERMINED GRAPHICALLY - A NOTE
    BIELESKI, IP
    NEW ZEALAND OPERATIONAL RESEARCH, 1982, 10 (02): : 143 - 151
  • [28] A generalized network flow model for the multi-mode resource-constrained project scheduling problem with discounted cash flows
    Chen, Miawjane
    Yan, Shangyao
    Wang, Sin-Siang
    Liu, Chiu-Lan
    ENGINEERING OPTIMIZATION, 2015, 47 (02) : 165 - 183
  • [29] Genetic Algorithm for a Discrete-Continuous Project Scheduling Problem with Discounted Cash Flows
    Waligora, Grzegorz
    2015 20TH INTERNATIONAL CONFERENCE ON METHODS AND MODELS IN AUTOMATION AND ROBOTICS (MMAR), 2015, : 52 - 57
  • [30] DISCOUNTED-CASH-FLOW RATES OF RETURN FOR VARYING CASH FLOWS
    NEAL, GW
    CHEMICAL ENGINEERING, 1982, 89 (26) : 73 - 75