A mixed integer linear programming model for short-term open pit mine production scheduling

被引:48
|
作者
Eivazy, H. [1 ]
Askari-Nasab, H. [1 ]
机构
[1] Univ Alberta, Min Optimizat Lab, Edmonton, AB, Canada
关键词
Short-term production scheduling; Mixed integer linear programming; Open pit; Cost minimisation;
D O I
10.1179/1743286312Y.0000000006
中图分类号
TD [矿业工程];
学科分类号
0819 ;
摘要
Short-term production scheduling in open pit mines usually generates a scheme to enable mining operations to deliver the budgeted tonnes and grades to the mill while following the long-term mine plan. The goal of this paper is to develop and test an optimisation model for short-term open pit mine production scheduling. A multidestination mixed integer linear programming (MILP) model is proposed, which minimises the overall cost of mining operations including mining, processing, haulage, rehandling and rehabilitation costs. The model is solved by branch-and-cut algorithm using TOMLAB/CPLEX optimiser. The model incorporates buffer and blending stockpiles, horizontal directional mining, and decisions on ramps while controlling technical constraints. A monthly production schedule in an iron ore mine is developed over 12 months to illustrate the practicality of the developed model. Three scenarios with different mining horizontal directions are considered. The scenario with minimum number of drop-cuts is selected as the best practical schedule.
引用
收藏
页码:97 / 108
页数:12
相关论文
共 50 条
  • [31] MINE SCHEDULING OPTIMIZATION WITH MIXED INTEGER PROGRAMMING
    GERSHON, ME
    [J]. MINING ENGINEERING, 1983, 35 (04) : 351 - 354
  • [32] A Mixed Integer Linear Programming Model for Production Scheduling of Non-Pipelined Wells
    Zhang, Zhiwei
    Tan, Chaodong
    Gao, Xiaoyong
    Zuo, Xin
    Chen, Tao
    [J]. 2019 IEEE 15TH INTERNATIONAL CONFERENCE ON CONTROL AND AUTOMATION (ICCA), 2019, : 1397 - 1404
  • [33] Mixed-Integer Nonlinear Programming for Head-Dependent Short-Term Hydro Scheduling
    Catalao, J. P. S.
    Pousinho, H. M. I.
    Mendes, V. M. F.
    [J]. 2009 INTERNATIONAL CONFERENCE ON POWER ENGINEERING, ENERGY AND ELECTRICAL DRIVES, 2009, : 90 - +
  • [34] A CHANCE CONSTRAINED INTEGER PROGRAMMING MODEL FOR OPEN PIT LONG-TERM PRODUCTION PLANNING
    Gholamnejad, J.
    Osanloo, M.
    Khorram, E.
    [J]. INTERNATIONAL JOURNAL OF ENGINEERING, 2008, 21 (04): : 407 - 418
  • [35] Life-of-mine optimization for integrated open stope development and production scheduling using a mixed-integer linear programming framework
    Appianing, Emmanuel John Andrew
    Ben-Awuah, Eugene
    Pourrahimian, Yashar
    [J]. MINING TECHNOLOGY-TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY, 2023, 132 (02) : 106 - 120
  • [36] A chance constrained Integer programming model for open pit long-term production planning
    Department of Mining and Metallurgical Engineering, Yazd University, P.O. Box 89195-741, Yazd, Iran
    不详
    不详
    [J]. Int. J. Eng. Trans. A Basics, 2008, 4 (407-418):
  • [37] A MIXED-INTEGER LINEAR PROGRAMMING (MILP) MODEL FOR SHORT-RANGE PRODUCTION SCHEDULING OF CEMENT QUARRY OPERATIONS
    Rehman, Safi Ur
    Asad, Mohammad Waqar Ali
    [J]. ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2010, 27 (03) : 315 - 333
  • [38] Mixed-integer Linear Programming Formulation for Short-term Scheduling of Cascaded Hydroelectric Plants with Pumped-storage Units
    Jia, Jiangtao
    [J]. ELECTRIC POWER COMPONENTS AND SYSTEMS, 2013, 41 (15) : 1456 - 1468
  • [39] Stochastic optimisation of long-term production scheduling for open pit mines with a new integer programming formulation
    Ramazan, S.
    Dimitrakopoulos, R.
    [J]. OREBODY MODELLING AND STRATEGIC MINE PLANNING: UNCERTAINTY AND RISK MANAGEMENT MODELS, 2005, (14): : 359 - 365
  • [40] Automatic formation of short-term plan based on the long-term plan on open-pit mine using 0-1 integer programming
    Sun, Xiao-Yu
    Zhang, Wei-Guo
    Chen, Yu
    Wang, Xia
    Sun, Meng-Hong
    [J]. Meitan Xuebao/Journal of the China Coal Society, 2012, 37 (07): : 1139 - 1143