The accuracy of risk-based cost estimation for water infrastructure projects: preliminary evidence from Australian projects

被引:25
|
作者
Liu, Li [1 ]
Napier, Zigrid [2 ]
机构
[1] Univ Sydney, Dept Civil Engn, Civil Engn Bldg J05, Sydney, NSW 2006, Australia
[2] Evans & Peck, Sydney, NSW, Australia
关键词
Cost estimating; forecasting; accuracy; risk-based estimating; fixed contingency approach;
D O I
10.1080/01446190903431525
中图分类号
F [经济];
学科分类号
02 ;
摘要
Infrastructure projects are still being plagued by cost overruns, delays and revenue shortfalls despite decades of practice and research. Risk-based estimating (RBE) is growing in popularity and has the potential to overcome the two main cost overrun factors-optimistic bias and strategic misrepresentation. Yet, little is known about the accuracy of RBE and its performance drivers. A comparison of water projects using RBE with a sample of construction projects using the conventional estimating approach shows that the projects estimated using RBE have better estimation accuracy than those estimated using more conventional approaches. In addition, the projects using RBE appear more likely to be under-budget while the ones using the conventional approach appear more likely to be over-budget. Further, through interviews and observations of the RBE process, three main performance drivers for the RBE method were identified to include outside view/collective experience, attention focusing and probabilistic, bottom-up modelling.
引用
下载
收藏
页码:89 / 100
页数:12
相关论文
共 50 条
  • [1] Risk Breakdown Matrix for Risk-Based Inspection of Transportation Infrastructure Projects
    Jeon, JungHo
    Zhang, Yuxi
    Yang, Liu
    Xu, Xin
    Cai, Hubo
    Tran, Dan
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2023, 149 (04)
  • [2] Cost Profiling of Water Infrastructure Projects
    Love, Peter E. D.
    Ahiaga-Dagbui, Dominic D.
    Smith, Simon D.
    Sing, Michael C. -P
    Tokede, Olubukola
    JOURNAL OF INFRASTRUCTURE SYSTEMS, 2018, 24 (04)
  • [3] Cost estimation methods of transport infrastructure projects
    Rónai, Péter
    Periodica Polytechnica Transportation Engineering, 2001, 29 (1-2): : 107 - 116
  • [4] Risk-Based Decision Analysis in the Design of Water Supply Projects
    Latinopoulos, P.
    Mylopoulos, N.
    Mylopoulos, Y.
    WATER RESOURCES MANAGEMENT, 1997, 11 (04) : 263 - 281
  • [5] Risk-Based Decision Analysis in the Design of Water Supply Projects
    P. Latinopoulos
    N. Mylopoulos
    Y. Mylopoulos
    Water Resources Management, 1997, 11 : 263 - 281
  • [6] Evolution of Risk-Based Cost and Schedule Estimates for North American Infrastructure Projects: What Have We Learned?
    Keizur, Alan E.
    Roberds, William J.
    INTERNATIONAL CONFERENCE ON TRANSPORTATION AND DEVELOPMENT 2021: TRANSPORTATION PLANNING AND DEVELOPMENT, 2021, : 145 - 156
  • [7] Risk-Based Approach to Predict the Cost Performance of Modularization in Construction Projects
    Abdul Nabi, Mohamad
    El-adaway, Islam H.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (10)
  • [8] Risk Based Budgeting of Infrastructure Projects
    Xenidis, Yiannis
    Stavrakas, Eleftherios
    SELECTED PAPERS FROM THE 26TH IPMA (INTERNATIONAL PROJECT MANAGEMENT ASSOCIATION), WORLD CONGRESS, 2013, 74 : 478 - 487
  • [9] Improving the Accuracy of Early Cost Estimates on Transportation Infrastructure Projects
    Karaca, Ilker
    Gransberg, Douglas D.
    Jeong, H. David
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2020, 36 (05)
  • [10] Statistical Characteristics of Cost Contingency in Water Infrastructure Projects
    Baccarini, David
    Love, Peter E. D.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (03)