Experience in 110 - 500 kV overhead transmission line construction and renovation projects in the northern regions of Western Siberia

被引:0
|
作者
Grigor'ev V.S. [1 ]
Ol'shanskii V.G. [1 ]
Starostenkov A.D. [1 ]
Khromyshev N.K. [1 ]
Shevtsov K.P. [1 ]
机构
[1] JSC Institute Energosetproject, Moscow
来源
Power Technol. Eng. | 2012年 / 4卷 / 317-320期
关键词
Engineering survey; Overhead power transmission line; Permafrost; Pile foundation; Transmission tower;
D O I
10.1007/s10749-012-0352-7
中图分类号
学科分类号
摘要
This is the first paper is a series of publications on our experience in the construction and renovation of 110 - 500 kV overhead transmission lines in the northern regions of West Siberia. The paper addresses problems related to the pile foundations of transmission towers erected on thawed or permafrost soil. The mechanisms of foundation-soil interaction, causes of accidents, and preventive measures are analyzed. © 2012 Springer Science + Business Media New York.
引用
收藏
页码:317 / 320
页数:3
相关论文
共 19 条
  • [1] Problems of design, construction, and operation of the foundations of transmission towers in the northern regions of Western Siberia
    Khromyshev N.K.
    Ol’shanskii V.G.
    Stolpovskaya E.V.
    [J]. Power Technology and Engineering, 2015, 49 (2) : 150 - 152
  • [2] Problems and countermeasures in construction of transmission line projects in permafrost regions
    GuoShang Wang
    QiHao Yu
    YanHui You
    Ze Zhang
    Lei Guo
    ShiJun Wang
    Yong Yu
    [J]. Sciences in Cold and Arid Regions, 2014, 6 (05) : 432 - 439
  • [3] Mitigation of Magnetic Field under Egyptian 500kV Overhead Transmission Line
    El Dein, Adel Z.
    [J]. WORLD CONGRESS ON ENGINEERING, WCE 2010, VOL II, 2010, : 956 - 961
  • [4] Line arresters and underbuilt wire application in lightning protection of 110 kV and 220 kV overhead transmission lines
    Banjanin, Mladen
    [J]. 2019 18TH INTERNATIONAL SYMPOSIUM INFOTEH-JAHORINA (INFOTEH), 2019,
  • [5] Analysis of current ampacity of the 110 kV overhead transmission line using a multiple regression model
    Malska, Wiesawa
    [J]. ELECTRIC POWER SYSTEMS RESEARCH, 2024, 236
  • [6] Lightning study and experience on the first 500kV Transmission Line Arrester in Malaysia
    Rawi, Iryani Mohamed
    Ab Kadir, M. Z. A.
    Azis, Norhafiz
    [J]. 2014 INTERNATIONAL CONFERENCE ON LIGHTNING PROTECTION (ICLP), 2014, : 1106 - 1109
  • [7] Analysis of the Conductor Tension During Galloping for a 500kV 6-bundled Overhead Transmission Line
    Yang, Xiaohui
    Zhang, Bo
    Yang, Wei
    Fu, Zhengcai
    [J]. RECENT ADVANCES IN ELECTRICAL & ELECTRONIC ENGINEERING, 2014, 7 (01) : 10 - 19
  • [8] Prediction of Egyptian 500-kV Overhead Transmission Line's Radio Interference by Using the Excitation Function
    El Dein, Adel Z.
    [J]. INTERNATIONAL JOURNAL OF EMERGING ELECTRIC POWER SYSTEMS, 2013, 14 (04): : 303 - 308
  • [9] Simulation of Lightning Transients on 110 kV overhead-cable transmission line using ATP-EMTP
    Fekete, Kresimir
    Nikolovski, Srete
    Knezevic, Goran
    Stojkov, Marinko
    Kovac, Zoran
    [J]. MELECON 2010: THE 15TH IEEE MEDITERRANEAN ELECTROTECHNICAL CONFERENCE, 2010, : 856 - 861
  • [10] RELAY SETTING CONSIDERATIONS AND OPERATIONAL EXPERIENCE OF A LONG 500KV TRANSMISSION-LINE
    MUSTAPHI, KK
    ZIMERING, R
    [J]. IEEE TRANSACTIONS ON POWER DELIVERY, 1988, 3 (01) : 111 - 120