Construction time–cost–resources–quality trade-off optimization using NSGA-III

被引:0
|
作者
Trivedi M.K. [1 ]
Sharma K. [1 ]
机构
[1] Department of Civil Engineering, Madhav Institute of Technology and Science, Gwalior
关键词
Competing objectives; Construction projects; MOSM; NSGA-III; Optimization;
D O I
10.1007/s42107-023-00731-0
中图分类号
学科分类号
摘要
For successful completion of construction project, achieving the project in minimum duration (time) and budget (cost) are oldest and of paramount importance objectives. But due to advancement in technologies and increasing requirements of project’s stakeholders/participants, there may be requirement of fulfilling more competing and conflicting objectives, such as reduction in amount of resource utilization and maximizing the project’s quality as well as minimizing the time and cost of project. Literature study shows numerous many-objective scheduling models (MOSMs) with several complexities and limitations. But due to increment in competing and conflicting objectives, such MOSM models are required which overcome the limitations and complexities of existing MOSM models. Therefore, this study introduces a non-dominated sorting genetic algorithm-III (NSGA-III)-based MOSM for the simultaneous optimization of time, cost, resources and quality. To demonstrate the working of proposed MOSM, it is practically implemented on a real construction project and a Pareto-optimal set of solution is obtained. Results of case study indicate the effectiveness of proposed MOSM in simultaneous optimization of four objectives. © 2023, The Author(s), under exclusive licence to Springer Nature Switzerland AG.
引用
收藏
页码:3543 / 3555
页数:12
相关论文
共 50 条
  • [21] Stochastic construction time-cost trade-off analysis
    Feng, CW
    Liu, L
    Burns, SA
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) : 117 - 126
  • [22] Optimization of the NSGA-III Algorithm Using Adaptive Scheduling
    Zhang, Xijun
    Zhong, Yunfang
    Zhang, Baoqi
    Nie, Shengyuan
    [J]. ENGINEERING LETTERS, 2023, 31 (02) : 459 - 466
  • [23] Multiobjective Optimization of Time-Cost Trade-Off Using Harmony Search
    Geem, Zong Woo
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2010, 136 (06): : 711 - 716
  • [24] Modelling the resource constrained time-cost-quality-safety risk-environmental impact trade-off using opposition-based NSGA III
    Sharma K.
    Trivedi M.K.
    [J]. Asian Journal of Civil Engineering, 2023, 24 (8) : 3083 - 3098
  • [25] Using genetic algorithms to solve construction time-cost trade-off problems
    Feng, CW
    Liu, LA
    Burns, SA
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) : 184 - 189
  • [26] Using genetic algorithms to solve construction time-cost trade-off problems
    Univ of Illinois at Urbana-Champaign, Urbana, United States
    [J]. J Comput Civ Eng, 3 (184-189):
  • [27] Solving Fuzzy Time–Cost Trade-Off in Construction Projects Using Linear Programming
    Elkalla I.
    Elbeltagi E.
    El Shikh M.
    [J]. Journal of The Institution of Engineers (India): Series A, 2021, 102 (1) : 267 - 278
  • [28] Hybrid time-quality-cost trade-off problems
    Kosztyan, Zsolt T.
    Szalkai, Istvan
    [J]. OPERATIONS RESEARCH PERSPECTIVES, 2018, 5 : 306 - 318
  • [29] Trade-off between quality and cost
    Huang, YF
    [J]. QUALITY & QUANTITY, 2001, 35 (03) : 265 - 276
  • [30] Trade-off between Quality and Cost
    Ying-Fang Huang
    [J]. Quality and Quantity, 2001, 35 : 265 - 276