The Multi-Mode Resource-Constrained Multi-Project Scheduling ProblemThe MISTA 2013 challenge

被引:0
|
作者
Tony Wauters
Joris Kinable
Pieter Smet
Wim Vancroonenburg
Greet Vanden Berghe
Jannes Verstichel
机构
[1] KU Leuven,Department of Computer Science, CODeS
来源
Journal of Scheduling | 2016年 / 19卷
关键词
Project scheduling; Multi-mode; Multi-project; Heuristics; Competition;
D O I
暂无
中图分类号
学科分类号
摘要
Scheduling projects is a difficult and time consuming process, and has far-reaching implications for any organization’s operations. By generalizing various aspects of project scheduling, decision makers are enabled to capture reality and act accordingly. In the context of the MISTA 2013 conference, the first MISTA challenge, organized by the authors, introduced such a general problem model: the Multi-Mode Resource-Constrained Multi-Project Scheduling Problem (MRCMPSP). The present paper reports on the competition and provides a discussion on its results. Furthermore, it provides an analysis of the submitted algorithms, and a study of their common elements. By making all benchmark datasets and results publicly available, further research on the MRCMPSP is stimulated.
引用
收藏
页码:271 / 283
页数:12
相关论文
共 50 条
  • [1] The Multi-Mode Resource-Constrained Multi-Project Scheduling Problem
    Wauters, Tony
    Kinable, Joris
    Smet, Pieter
    Vancroonenburg, Wim
    Vanden Berghe, Greet
    Verstichel, Jannes
    [J]. JOURNAL OF SCHEDULING, 2016, 19 (03) : 271 - 283
  • [2] A Decomposition Method for the Multi-Mode Resource-Constrained Multi-Project Scheduling Problem (MRCMPSP)
    Kuehn, Mathias
    Dirkmann, Sebastian
    Voelker, Michael
    Schmidt, Thorsten
    [J]. OPERATIONS RESEARCH PROCEEDINGS 2016, 2018, : 521 - 526
  • [3] A Benders decomposition algorithm for the multi-mode resource-constrained multi-project scheduling problem with uncertainty
    Sadeghloo, Maryam
    Emami, Saeed
    Divsalar, Ali
    [J]. ANNALS OF OPERATIONS RESEARCH, 2024, 339 (03) : 1637 - 1677
  • [4] Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem
    Kannimuthu, Marimuthu
    Raphael, Benny
    Ekambaram, Palaneeswaran
    Kuppuswamy, Ananthanarayanan
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2020, 27 (04) : 893 - 916
  • [5] Multi-mode resource constrained multi-project scheduling and resource portfolio problem
    Besikci, Umut
    Bilge, Umit
    Ulusoy, Gunduz
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 240 (01) : 22 - 31
  • [6] Simulated Annealing for Multi-Mode Resource-Constrained Project Scheduling
    Joanna Józefowska
    Marek Mika
    Rafał Różycki
    Grzegorz Waligóra
    Jan Węglarz
    [J]. Annals of Operations Research, 2001, 102 : 137 - 155
  • [7] Resource-constrained project scheduling: a heuristic for the multi-mode case
    Heilmann, R
    [J]. OR SPEKTRUM, 2001, 23 (03): : 335 - 357
  • [8] Simulated annealing for multi-mode resource-constrained project scheduling
    Józefowska, J
    Mika, M
    Rózycki, R
    Waligóra, G
    Weglarz, J
    [J]. ANNALS OF OPERATIONS RESEARCH, 2001, 102 (1-4) : 137 - 155
  • [9] Modelling and Solving Multi-mode Resource-Constrained Project Scheduling
    Szeredi, Ria
    Schutt, Andreas
    [J]. PRINCIPLES AND PRACTICE OF CONSTRAINT PROGRAMMING, CP 2016, 2016, 9892 : 483 - 492
  • [10] Hybrid Heuristics for Multi-mode Resource-Constrained Project Scheduling
    Tchao, Celso
    Martins, Simone L.
    [J]. LEARNING AND INTELLIGENT OPTIMIZATION, 2008, 5313 : 234 - +