Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities

被引:0
|
作者
Olivier Lambrechts
Erik Demeulemeester
Willy Herroelen
机构
[1] Katholieke Universiteit Leuven,Department of Decision Sciences and Information Management, Research Center for Operations Management, Faculty of Economics and Applied Economics
来源
Journal of Scheduling | 2008年 / 11卷
关键词
Proactive/reactive project scheduling; Stochastic resource breakdowns;
D O I
暂无
中图分类号
学科分类号
摘要
Research concerning project planning under uncertainty has primarily focused on the stochastic resource-constrained project scheduling problem (stochastic RCPSP), an extension of the basic RCPSP, in which the assumption of deterministic activity durations is dropped. In this paper, we introduce a new variant of the RCPSP, for which the uncertainty is modeled by means of resource availabilities that are subject to unforeseen breakdowns. Our objective is to build a robust schedule that meets the project deadline and minimizes the schedule instability cost, defined as the expected weighted sum of the absolute deviations between the planned and the actually realized activity starting times during project execution. We describe how stochastic resource breakdowns can be modeled, which reaction is recommended, when a resource infeasibility occurs due to a breakdown, and how one can protect the initial schedule from the adverse effects of potential breakdowns. An extensive computational experiment is used to show the relative performance of the proposed proactive and reactive strategies. It is shown that protection of the baseline schedule, coupled with intelligent schedule recovery, yields significant performance gains over the use of deterministic scheduling approaches in a stochastic setting.
引用
收藏
页码:121 / 136
页数:15
相关论文
共 50 条
  • [1] Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities
    Lambrechts, Olivier
    Demeulemeester, Erik
    Herroelen, Willy
    [J]. JOURNAL OF SCHEDULING, 2008, 11 (02) : 121 - 136
  • [2] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    [J]. Journal of Scheduling, 2019, 22 : 211 - 237
  • [3] The proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    [J]. JOURNAL OF SCHEDULING, 2019, 22 (02) : 211 - 237
  • [4] The Proactive Resource-Constrained Project Scheduling Problem with Resource Transfer Times
    Ma, Zhiqiang
    He, Zhengwen
    Wang, Nengmin
    [J]. PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 642 - 647
  • [5] Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    [J]. ANNALS OF OPERATIONS RESEARCH, 2019, 274 (1-2) : 187 - 210
  • [6] Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    [J]. Annals of Operations Research, 2019, 274 : 187 - 210
  • [7] Preemption resource-constrained project scheduling problems with fuzzy random duration and resource availabilities
    Chen, Lu
    Zhang, Zhe
    [J]. JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2016, 33 (06) : 373 - 382
  • [8] Proactive policies for the stochastic resource-constrained project scheduling problem
    Deblaere, Filip
    Demeulemeester, Erik
    Herroelen, Willy
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 214 (02) : 308 - 316
  • [9] New strategies for stochastic resource-constrained project scheduling
    Salim Rostami
    Stefan Creemers
    Roel Leus
    [J]. Journal of Scheduling, 2018, 21 : 349 - 365
  • [10] A reactive scheduling approach for the resource-constrained project scheduling problem with dynamic resource disruption
    Xu, Jiaojiao
    Bai, Sijun
    [J]. KYBERNETES, 2024, 53 (06) : 2007 - 2028