Time-cost trade-off via optimal control theory in Markov PERT networks

被引:0
|
作者
Amir Azaron
Hideki Katagiri
Masatoshi Sakawa
机构
[1] University of Bu-Ali-Sina,Department of Industrial Engineering, Faculty of Engineering
[2] Dalhousie University,Department of Industrial Engineering
[3] Hiroshima University,Graduate School of Engineering
来源
关键词
Project management; Multiple objective programming; Optimal control theory; Markov processes;
D O I
暂无
中图分类号
学科分类号
摘要
We develop a new analytical model for the time-cost trade-off problem via optimal control theory in Markov PERT networks. It is assumed that the activity durations are independent random variables with generalized Erlang distributions, in which the mean duration of each activity is a non-increasing function of the amount of resource allocated to it. Then, we construct a multi-objective optimal control problem, in which the first objective is the minimization of the total direct costs of the project, in which the direct cost of each activity is a non-decreasing function of the resources allocated to it, the second objective is the minimization of the mean of project completion time and the third objective is the minimization of the variance of project completion time. Finally, two multi-objective decision techniques, viz, goal attainment and goal programming are applied to solve this multi-objective optimal control problem and obtain the optimal resources allocated to the activities or the control vector of the problem
引用
收藏
页码:47 / 64
页数:17
相关论文
共 50 条
  • [1] Time-cost trade-off via optimal control theory in Markov PERT networks
    Azaron, Amir
    Katagiri, Hideki
    Sakawa, Masatoshi
    [J]. ANNALS OF OPERATIONS RESEARCH, 2007, 150 (01) : 47 - 64
  • [2] A genetic algorithm approach for the time-cost trade-off in PERT networks
    Azaron, A
    Perkgoz, C
    Sakawa, M
    [J]. APPLIED MATHEMATICS AND COMPUTATION, 2005, 168 (02) : 1317 - 1339
  • [3] Time-cost trade-off in PERT networks using a genetic algorithm
    Azaron, A
    Perkgoz, C
    Kato, K
    Katagiri, H
    Sakawa, M
    [J]. 2004 47TH MIDWEST SYMPOSIUM ON CIRCUITS AND SYSTEMS, VOL III, CONFERENCE PROCEEDINGS, 2004, : 57 - 60
  • [4] A discrete-time approximation technique for the time-cost trade-off in pert networks
    Azaron, Amir
    Sakawa, Masatoshi
    Tavakkoli-Moghaddam, Reza
    Safaei, Nima
    [J]. RAIRO-OPERATIONS RESEARCH, 2007, 41 (01) : 61 - 81
  • [5] Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach
    Azaron, Amir
    Tavakkoli-Moghaddam, Reza
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 180 (03) : 1186 - 1200
  • [6] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    [J]. JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222
  • [7] AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY
    Lin, Chien-Liang
    Lai, Yu-Che
    [J]. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2020, 26 (02) : 113 - 130
  • [8] A New Idea to LP Model for Time-cost Trade-off in Networks
    ZHAO Guohao
    JING Shentu and ZHANG Yaguang(Scanxi Institute of Economic Management
    [J]. Journal of Systems Science and Systems Engineering, 1995, (03) : 250 - 255
  • [9] Time-cost trade-off analysis of project networks in fuzzy environments
    Chen, Shih-Pin
    Tsai, Ming-Jiun
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 212 (02) : 386 - 397
  • [10] A fuzzy time-cost trade-off problem with credibility theory concepts
    Ke, Hua
    Ma, Weimin
    [J]. PROCEEDING OF THE SEVENTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2008, 7 : 258 - 262