Application of the surrogate gradient method for a multi-item single-machine dynamic lot size scheduling problem

被引:0
|
作者
Minoru Kobayashi
机构
[1] Fukuoka Institute of Technology,
来源
SN Applied Sciences | 2021年 / 3卷
关键词
Lagrangian decomposition and coordination method; Production scheduling; Acceleration; Dummy item;
D O I
暂无
中图分类号
学科分类号
摘要
This study treats a multi-item single-machine dynamic lot size scheduling problem with sequence-independent setup cost and setup time. This problem has various heterogeneous decision features, such as lot sizing and lot sequencing. Traditionally, the problem has been treated by putting artificial constraints on the other feature in order to determine one of them. The proposed model is a Lagrange decomposition and coordination method that aims at simultaneous optimization of these decision features; however, smooth convergence to a feasible near-optimal solution has been a problem. So, in this paper, we propose a model that improves the constraint equation of the existing model and showed that it satisfies the Karush–Kuhn–Tucker (KKT) condition when we obtained a feasible solution. In addition, by applying the surrogate gradient method, which has never been applied to this problem before, it was shown that smoother convergence than before can be achieved through actual example of printed circuit board.
引用
收藏
相关论文
共 50 条
  • [21] MULTI-ITEM LOT SIZE SCHEDULING BY HEURISTIC .1. WITH FIXED RESOURCES
    NEWSON, EFP
    MANAGEMENT SCIENCE SERIES B-APPLICATION, 1975, 21 (10): : 1186 - 1193
  • [22] Dynamic lot size/sequencing policies in a multi-product, single-machine system
    North Carolina State Univ, Raleigh, United States
    IIE Transactions (Institute of Industrial Engineers), 1997, 29 (02): : 127 - 137
  • [23] Dynamic lot size/sequencing policies in a multi-product, single-machine system
    Hodgson, TJ
    Ge, G
    King, RE
    Said, H
    IIE TRANSACTIONS, 1997, 29 (02) : 127 - 137
  • [24] NUMERICAL EVALUATION OF HEURISTICS FOR THE MULTI-ITEM SINGLE-LEVEL CAPACITATED LOT-SIZE PROBLEM
    GUNTHER, HO
    ENGINEERING COSTS AND PRODUCTION ECONOMICS, 1988, 14 (03): : 233 - 243
  • [25] Expected time in system analysis of a single-machine multi-item processing center
    Kuik, R
    Tielemans, PFJ
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 156 (02) : 287 - 304
  • [26] EOQ-based inventory management in single-machine multi-item systems
    Rossi, Tommaso
    Pozzi, Rossella
    Testa, Mariapaola
    OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2017, 71 : 106 - 113
  • [27] A HEURISTIC SCHEDULING POLICY FOR MULTI-ITEM, SINGLE-MACHINE PRODUCTION SYSTEMS WITH TIME-VARYING, STOCHASTIC DEMANDS
    LEACHMAN, RC
    GASCON, A
    MANAGEMENT SCIENCE, 1988, 34 (03) : 377 - 390
  • [28] Forecast horizon of multi-item dynamic lot size model with perishable inventory
    Jing, Fuying
    Lan, Zirui
    PLOS ONE, 2017, 12 (11):
  • [29] SCHEDULING A SINGLE MACHINE SYSTEM - MULTI-PRODUCT MULTI-ITEM CASE
    GOYAL, SK
    OPERATIONAL RESEARCH QUARTERLY, 1975, 26 (03) : 619 - 627
  • [30] Single-machine scheduling problem with multi-RMAs
    Wu, Hua-Ping
    Huang, Min
    Wang, Xing-Wei
    Kongzhi yu Juece/Control and Decision, 2014, 29 (12): : 2253 - 2258