Preventive maintenance scheduling of multi-component systems with interval costs

被引:69
|
作者
Gustavsson, Emil
Patriksson, Michael
Stromberg, Ann-Brith [1 ]
Wojciechowski, Adam
Onnheim, Magnus
机构
[1] Chalmers, Dept Math Sci, Gothenburg, Sweden
关键词
Maintenance scheduling; Integer optimization; Finite horizon; Dynamic grouping; Polyhedral analysis; Case studies; JOINT REPLENISHMENT PROBLEM; ALGORITHMS; MODELS;
D O I
10.1016/j.cie.2014.02.009
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
We introduce the preventive maintenance scheduling problem with interval costs (PMSPIC), which is to schedule preventive maintenance (PM) of the components of a system over a finite and discretized time horizon, given a common set-up cost and component costs dependent on the lengths of the maintenance intervals. We present a 0-1 integer linear programming (0-1 ILP) model for the PMSPIC; the model is identical to that presented by Joneja (1990) for the joint replenishment problem within inventory management. We study this model from a polyhedral and exact solutions' point of view, as opposed to previously studied heuristics (e.g. Boctor, Laporte, & Renaud, 2004; Federgruen & Tzur, 1994; Levi, Roundy, & Shmoys, 2006; Joneja, 1990). We show that most of the integrality constraints can be relaxed and that the linear inequality constraints define facets of the convex hull of the feasible set. We further relate the PMSPIC to the opportunistic replacement problem, for which detailed polyhedral studies were performed by Almgren et al. (2012a). The PMSPIC can be used as a building block to model several types of maintenance planning problems possessing deterioration costs. By a careful modeling of these costs, a poly-hedrally sound 0-1 ILP model is used to find optimal solutions to realistic-sized multi-component maintenance planning problems. The PMSPIC is thus easily extended by side-constraints or to multiple tiers, which is demonstrated through three applications; these are chosen to span several levels of unmodeled randomness requiring fundamentally different maintenance policies, which are all handled by variations of our basic model. Our first application considers rail grinding. Rail cracks increase with increasing intervals between grinding occasions, implying that more grinding passes must be performed thus generating higher costs. We optimize the grinding schedule for a set of track sections presuming a deterministic model for crack growth; hence, no corrective maintenance (CM) will occur between the grinding occasions scheduled. The second application concerns two approaches for scheduling component replacements in aircraft engines. The first approach is bi-objective, simultaneously minimizing the cost for the scheduled PM and the probability of unexpected stops. In the second approach the sum of costs for PM and expected CM without rescheduling is minimized. When rescheduling is allowed, the 0-1 1LP model is used as a policy by re-optimizing the schedule at a component failure, which then constitutes an opportunity for PM. The policy manages the trade-off between costs for PM and unplanned CM and is evaluated in a simulation of the engine. The third application considers components' replacement in wind mills in a wind farm, extending the PMSPIC to comprise multiple tiers with joint set-up costs. Due to the large number of components unexpected stops occur frequently, thus calling for a dynamic rescheduling, which is evaluated through a simulation of the system. In each of the three applications, the use of the 0-1 ILP model is compared with age or constant-interval policies; the maintenance costs are reduced by up to 16% as compared with the respective best simple policy. The results are strongest for the first two applications, possessing low levels of unmodeled randomness. (C) 2014 Elsevier Ltd. All rights reserved.
引用
收藏
页码:390 / 400
页数:11
相关论文
共 50 条
  • [41] Preventive maintenance optimization for a multi-component system under changing job shop schedule
    Zhou, Xiaojun
    Lu, Zhiqiang
    Xi, Lifeng
    RELIABILITY ENGINEERING & SYSTEM SAFETY, 2012, 101 : 14 - 20
  • [42] Opportunistic Preventive Maintenance Strategy of a Multi-Component System with Hierarchical Structure by Simulation and Evaluation
    Barde, Stephane
    Shin, Hayong
    Yacout, Soumaya
    2016 IEEE 21ST INTERNATIONAL CONFERENCE ON EMERGING TECHNOLOGIES AND FACTORY AUTOMATION (ETFA), 2016,
  • [43] Opportunistic policy for optimal preventive maintenance of a multi-component system in continuous operating units
    Laggoune, Radouane
    Chateauneuf, Alaa
    Aissani, Djamil
    COMPUTERS & CHEMICAL ENGINEERING, 2009, 33 (09) : 1499 - 1510
  • [44] Dynamic influences in multi-component maintenance
    Wildeman, RE
    Dekker, R
    QUALITY AND RELIABILITY ENGINEERING INTERNATIONAL, 1997, 13 (04) : 199 - 207
  • [45] A review of multi-component maintenance models
    Nicolai, R. P.
    Dekker, R.
    RISK, RELIABILITY AND SOCIETAL SAFETY, VOLS 1-3: VOL 1: SPECIALISATION TOPICS; VOL 2: THEMATIC TOPICS; VOL 3: APPLICATIONS TOPICS, 2007, : 289 - 296
  • [46] Scheduling Preventive Maintenance as a Function of an Imperfect Inspection Interval
    He, Kai
    Maillart, Lisa M.
    Prokopyev, Oleg A.
    IEEE TRANSACTIONS ON RELIABILITY, 2015, 64 (03) : 983 - 997
  • [47] Scheduling multi-component applications with mobile agents in heterogeneous distributed systems
    Ezugwu, Absalom E.
    Junaidu, Sahalu B.
    Frincu, Marc E.
    Buhari, Seyed M.
    Obiniyi, Afolayan A.
    CONCURRENCY AND COMPUTATION-PRACTICE & EXPERIENCE, 2016, 28 (05): : 1462 - 1479
  • [48] Prognostic control-enhanced maintenance optimization for multi-component systems
    Niu, Gang
    Jiang, Junjie
    RELIABILITY ENGINEERING & SYSTEM SAFETY, 2017, 168 : 218 - 226
  • [49] Decision support for multi-component systems: visualizing interdependencies for predictive maintenance
    Gashi, Milot
    Mutlu, Belgin
    Lindstaedt, Stefanie
    Thalmann, Stefan
    PROCEEDINGS OF THE 55TH ANNUAL HAWAII INTERNATIONAL CONFERENCE ON SYSTEM SCIENCES, 2022, : 1706 - 1715
  • [50] Outsourcing selective maintenance problem in failure prone multi-component systems
    Chaabane, K.
    Khatab, A.
    Aghezzaf, E. H.
    Diallo, C.
    Venkatadri, U.
    IFAC PAPERSONLINE, 2018, 51 (11): : 525 - 530