Tractable Risk Measures for the Selective Scheduling Problem with Sequence-Dependent Setup Times

被引:0
|
作者
Bruni, M. E. [1 ]
Khodaparasti, S. [1 ]
机构
[1] Univ Calabria, Dept Mech Energy & Management Engn, Arcavacata Di Rende, Italy
关键词
Machine scheduling; Risk measure; Heuristic; VALUE-AT-RISK; ORDER ACCEPTANCE; ROBUST; OPTIMIZATION;
D O I
10.1007/978-3-030-37584-3_4
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Quantifying and minimizing the risk is a basic problem faced in a wide range of applications. Once the risk is explicitly quantified by a risk measure, the crucial and ambitious goal is to obtain risk-averse solutions, given the computational hurdle typically associated with optimization problems under risk. This is especially true for many difficult combinatorial problems, and notably for scheduling problems. This paper aims to present a few tractable risk measures for the selective scheduling problem with parallel identical machines and sequence-dependent setup times. We indicate how deterministic reformulations can be obtained when the distributional information is limited to first and second-order moment information for a broad class of risk measures. We propose an efficient heuristic for addressing the computational difficulty of the resulting models and we showcase the practical applicability of the proposed approach providing computational evidence on a set of benchmark instances.
引用
收藏
页码:70 / 84
页数:15
相关论文
共 50 条
  • [31] Scheduling job shop problems with sequence-dependent setup times
    Naderi, B.
    Zandieh, M.
    Ghomi, S. M. T. Fatemi
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2009, 47 (21) : 5959 - 5976
  • [32] Flow shop batching and scheduling with sequence-dependent setup times
    Liji Shen
    Jatinder N. D. Gupta
    Udo Buscher
    Journal of Scheduling, 2014, 17 : 353 - 370
  • [33] Scheduling unrelated parallel machines with sequence-dependent setup times
    Zeidi, Javad Rezaeian
    MohammadHosseini, Samir
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2015, 81 (9-12): : 1487 - 1496
  • [34] Parallel Machines Scheduling with Sequence-Dependent Setup Times Constraints
    Hu, Dayong
    Yao, Zhenqiang
    ADVANCED SCIENCE LETTERS, 2011, 4 (6-7) : 2528 - 2531
  • [35] Scheduling flexible flow lines with sequence-dependent setup times
    Kurz, ME
    Askin, RG
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 159 (01) : 66 - 82
  • [36] A deadlock-free scheduling with sequence-dependent setup times
    Zhang, Hehua
    Gu, Ming
    Song, Xiaoyu
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 45 (5-6): : 593 - 602
  • [37] Scheduling jobs on parallel machines with sequence-dependent setup times
    Lee, YH
    Pinedo, M
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1997, 100 (03) : 464 - 474
  • [38] Scheduling unrelated parallel machines with sequence-dependent setup times
    Javad Rezaeian Zeidi
    Samir MohammadHosseini
    The International Journal of Advanced Manufacturing Technology, 2015, 81 : 1487 - 1496
  • [39] Flow shop batching and scheduling with sequence-dependent setup times
    Shen, Liji
    Gupta, Jatinder N. D.
    Buscher, Udo
    JOURNAL OF SCHEDULING, 2014, 17 (04) : 353 - 370
  • [40] CONSTRAINT BASED SCHEDULING IN A GENETIC ALGORITHM FOR THE SINGLE MACHINE SCHEDULING PROBLEM WITH SEQUENCE-DEPENDENT SETUP TIMES
    Sioud, Aymen
    Gravel, Marc
    Gagne, Caroline
    ICEC 2010: PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON EVOLUTIONARY COMPUTATION, 2010, : 137 - 145